Difference between revisions of "Bubble Chamber Meeting Wednesday July 1, 2015"
Jump to navigation
Jump to search
Line 34: | Line 34: | ||
# List of fluids: | # List of fluids: | ||
## Mercury: 150 mL | ## Mercury: 150 mL | ||
− | ## Superheated liquid (N<sub>2</sub>O or C<sub> | + | ## Superheated liquid (N<sub>2</sub>O or C<sub>2</sub>F<sub>6</sub>): 40 – 60 mL |
## Hydraulic fluid: 5 gl | ## Hydraulic fluid: 5 gl | ||
## Silicon fluid for Chiller: 2 L | ## Silicon fluid for Chiller: 2 L |
Revision as of 11:59, 5 July 2015
We will meet in TL 2221 on Wednesday July 1 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Made the 27" stand for JLab Injector beamline
- Ready to start crating, expect to ship by mid-July
- Upon arrival at JLab, move to Injector tunnel
- Brad will provide description of the shipment and handling instruction
- Brad will be at JLab August 3 – 12.
- Safety Reviews:
- Started pressure system approval process
- Will need Electrical Review since we have 208 V custom-made electrical distribution box
- Need a TOSP with all the operational and safety procedures (fire, ...)
- List of fluids:
- Mercury: 150 mL
- Superheated liquid (N2O or C2F6): 40 – 60 mL
- Hydraulic fluid: 5 gl
- Silicon fluid for Chiller: 2 L
- Cancelled shifts of beam scheduled for August except for swing shifts in second week