Line 31: | Line 31: | ||
# Started pressure system approval process | # Started pressure system approval process | ||
# Will need Electrical Review since we have 208 V custom-made electrical distribution box | # Will need Electrical Review since we have 208 V custom-made electrical distribution box | ||
− | # Need a TOSP with all the operational and safety procedures (fire, ...) | + | # Need a TOSP with all the operational and safety procedures (fire, power loss, ...) |
# List of fluids: | # List of fluids: | ||
## Mercury: 150 mL | ## Mercury: 150 mL |
Revision as of 12:04, 5 July 2015
We will meet in TL 2221 on Wednesday July 1 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Made the 27" stand for JLab Injector beamline
- Ready to start crating, expect to ship by mid-July
- Upon arrival at JLab, move to Injector tunnel
- Brad will provide description of the shipment and handling instruction
- Brad will be at JLab August 3 – 12.
- Safety Reviews:
- Started pressure system approval process
- Will need Electrical Review since we have 208 V custom-made electrical distribution box
- Need a TOSP with all the operational and safety procedures (fire, power loss, ...)
- List of fluids:
- Mercury: 150 mL
- Superheated Liquid (N2O or C2F6): 40 – 60 mL
- Hydraulic Fluid: 5 gal
- Silicone Oil for Chiller: 2 L
- Cancelled shifts of beam scheduled for August except for swing shifts in second week