(Created page with " '''== What do we need to connect the beamline to the gunr? ==''' *Fixing the gun in its final position to the table *Install the anode *Install recently fabricated "viewer p...") |
|||
Line 1: | Line 1: | ||
− | '''== What do we need | + | '''== What do we need for connecting the beamline to the gunr? ==''' |
*Fixing the gun in its final position to the table | *Fixing the gun in its final position to the table | ||
Line 7: | Line 7: | ||
*Install 4-1/2 inch valve between the anode flange and the beamline | *Install 4-1/2 inch valve between the anode flange and the beamline | ||
*The beamline height can be defined by the final height of the center line of the cathode, defined by gun-table assembly. We can then adjust the beamline height (80/20 adjustable feet) accordingly. | *The beamline height can be defined by the final height of the center line of the cathode, defined by gun-table assembly. We can then adjust the beamline height (80/20 adjustable feet) accordingly. | ||
− | *Can we do this before parts are ready to re-start high voltage testing? Who can do what? what help/assistance is needed? | + | *Can we do this with the existing beamline components before parts are ready to re-start high voltage testing? Who can do what? what help/assistance is needed? In parallel, we/I need to look for 2 DP cans...one more viewer screen, dump, steering coils, beampipe, hardware, what else??? |
Latest revision as of 13:13, 18 August 2015
== What do we need for connecting the beamline to the gunr? ==
- Fixing the gun in its final position to the table
- Install the anode
- Install recently fabricated "viewer ports" anode flange
- Install 4-1/2 inch valve between the anode flange and the beamline
- The beamline height can be defined by the final height of the center line of the cathode, defined by gun-table assembly. We can then adjust the beamline height (80/20 adjustable feet) accordingly.
- Can we do this with the existing beamline components before parts are ready to re-start high voltage testing? Who can do what? what help/assistance is needed? In parallel, we/I need to look for 2 DP cans...one more viewer screen, dump, steering coils, beampipe, hardware, what else???