(Created page with "* High current runs * Shutdown Plan: ## Install new YAG screen at viewer 3 ## Fix existing harp and install 20 µm tungsten wire ## Add a new CEBAF-style harp with 10 µm t...")
 
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
* High current runs
 
* High current runs
 +
 +
 +
* Sajini - Differential Orbits study:
 +
:: [[media:Sajini_different_orbits-corrector_settings_11Sept2017.pdf]]
 +
:: [[media:Sajini_different_orbits-corrector_settings_11Sept2017.xlsx]]
  
  
 
* Shutdown Plan:
 
* Shutdown Plan:
  
## Install new YAG screen at viewer 3
+
# Install new YAG screen at viewer 3
## Fix existing harp and install 20 µm tungsten wire
+
# Fix existing harp and install 20 µm tungsten wire
## Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps)
+
# Add a new CEBAF-style harp with 10 µm tungsten wire (''i.e'', GTS will have two harps)
## Replace leaky vent valve
+
# Replace leaky vent valve
## Replace bad ion pump
+
# Replace bad ion pump
 +
# Activate new photocathode (new puck): 5 mm active area at center or full active area?
  
  
 
* Next Shutdown – December 2017:
 
* Next Shutdown – December 2017:
## Install TE011 cavity
+
# Install TE011 cavity

Latest revision as of 09:42, 11 September 2017

  • High current runs


  • Sajini - Differential Orbits study:
media:Sajini_different_orbits-corrector_settings_11Sept2017.pdf
media:Sajini_different_orbits-corrector_settings_11Sept2017.xlsx


  • Shutdown Plan:
  1. Install new YAG screen at viewer 3
  2. Fix existing harp and install 20 µm tungsten wire
  3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
  4. Replace leaky vent valve
  5. Replace bad ion pump
  6. Activate new photocathode (new puck): 5 mm active area at center or full active area?


  • Next Shutdown – December 2017:
  1. Install TE011 cavity