* Progress:
 
* Progress:
**HV supply installed, with remote operation-completed
+
** HV supply installed, with remote operation-completed
**Macro pulsing wiring- completed
+
** Macro pulsing wiring- completed
**Fiber-optic communications wired and functioning- completed
+
** Fiber-optic communications wired and functioning- completed
**Gun installed with Josh's spool- completed
+
** Gun installed with Josh's spool- completed
**Hot deck constructed and installed -completed
+
** Hot deck constructed and installed -completed
**RF transmission line constructed and installed- completed
+
** RF transmission line constructed and installed- completed
**Troubleshooting DC voltages on hot deck- completed
+
** Troubleshooting DC voltages on hot deck- completed
**Gun under vacuum removal turbo- completed
+
** Gun under vacuum removal turbo- completed
  
  
 
* Remaining Tasks:
 
* Remaining Tasks:
**Cathode activation- waiting on Karl's instruction
+
** Cathode activation- waiting on Karl's instruction
**HV processing- needs to be after cathode activation
+
** HV processing- needs to be after cathode activation
**RF/macro pulsing troubleshooting- need scope and power meter
+
** RF/macro pulsing troubleshooting- need scope and power meter
**Survey and alignment- need to scheduled
+
** Survey and alignment- need to scheduled
 +
** Hot Deck OSP
 +
** Fiber-plastic corona cover
  
  
 
* Schedule:
 
* Schedule:
**RF troubleshooting as soon as I have required equipment. Start today?
+
** RF troubleshooting as soon as I have required equipment. Start today?
**Cathode activation- as soon as I get the required settings from Karl it will be completed the same day.
+
** Cathode activation- as soon as I get the required settings from Karl it will be completed the same day.
**HV processing- the day after cathode activation.
+
** HV processing (with cover and RadMon)- the day after cathode activation.
 
** survey and alignment- ideally Friday 7/19/19
 
** survey and alignment- ideally Friday 7/19/19
 +
 +
 +
* GTS Photocathode Analysis:
 +
:: [[media:CsxKySb_Photocathodes.pptx]]
 +
:: [[media:Yan_Wang_2019-07-11_12.21.11.doc]]

Latest revision as of 11:11, 15 July 2019

  • Progress:
    • HV supply installed, with remote operation-completed
    • Macro pulsing wiring- completed
    • Fiber-optic communications wired and functioning- completed
    • Gun installed with Josh's spool- completed
    • Hot deck constructed and installed -completed
    • RF transmission line constructed and installed- completed
    • Troubleshooting DC voltages on hot deck- completed
    • Gun under vacuum removal turbo- completed


  • Remaining Tasks:
    • Cathode activation- waiting on Karl's instruction
    • HV processing- needs to be after cathode activation
    • RF/macro pulsing troubleshooting- need scope and power meter
    • Survey and alignment- need to scheduled
    • Hot Deck OSP
    • Fiber-plastic corona cover


  • Schedule:
    • RF troubleshooting as soon as I have required equipment. Start today?
    • Cathode activation- as soon as I get the required settings from Karl it will be completed the same day.
    • HV processing (with cover and RadMon)- the day after cathode activation.
    • survey and alignment- ideally Friday 7/19/19


  • GTS Photocathode Analysis:
media:CsxKySb_Photocathodes.pptx
media:Yan_Wang_2019-07-11_12.21.11.doc