Line 11: Line 11:
 
2- Bubble Chamber Schedule at JLab
 
2- Bubble Chamber Schedule at JLab
  
3- How would the 5D beamline look for the Bubble Chamber test in October 2014?
+
3- How would the 5D beamline look for the Bubble Chamber beam test?
 
   
 
   
  
  
 +
----
  
* Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble
+
'''Notes from this meeting:'''
Chamber beamline, in the radiator chamber.
+
 
 +
* The new chiller did not arrive at Argonne yet.
 +
 
 +
* The Bubble Chamber safety reviews will be completed soon (Pressure System completed, waiting on Mercury Review) and a copy will be sent to JLab by the end of March to start the process here.
 +
 
 +
* Our Budget Request: [[media:Bubble_FinalCost.pdf]] [[media:Bubble_FinalCost.pptx]]
 +
  - Fast Vale and Dipole Magnet are approved as part of RSR/SRC.
 +
  - Other expenses (Super Harps, Dumps, ...) were included in the ARD/SRC request but not yet approved.
 +
 
 +
* Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble Chamber beamline, in the radiator chamber.
 +
 
 +
* Test Beamline:
 +
  - Ask for thermal analysis of the flange radiator to determine the operational beam current.
 +
  - Design collimator using GEANT4. Part of the collimator could be positioned inside the pressure vessel. At some point,
 +
    Argonne ordered Cu material that could be available for us.
 +
 
 +
* Test Schedule:
 +
  - Start the '''Experiment Readiness Review''' process with a meeting with Arne and Rolf.

Latest revision as of 13:40, 28 March 2014

We will meet in TL 2236 on Wednesday March 5 at 3:00 pm EST.

For those calling in we'll use the ReadyTalk audio conference system.

1. Dial Toll-Free Number: 866-740-1260 (U.S. & Canada)
2. Enter 7-digit access code 4402297, followed by “#”

Agenda:

1- Bubble Chamber progress at Argonne

2- Bubble Chamber Schedule at JLab

3- How would the 5D beamline look for the Bubble Chamber beam test?



Notes from this meeting:

  • The new chiller did not arrive at Argonne yet.
  • The Bubble Chamber safety reviews will be completed soon (Pressure System completed, waiting on Mercury Review) and a copy will be sent to JLab by the end of March to start the process here.
  - Fast Vale and Dipole Magnet are approved as part of RSR/SRC.
  - Other expenses (Super Harps, Dumps, ...) were included in the ARD/SRC request but not yet approved.
  • Fast Valve was ordered. The Valve will be installed upstream of DP cans. The gauge will be installed at the end of Bubble Chamber beamline, in the radiator chamber.
  • Test Beamline:
  - Ask for thermal analysis of the flange radiator to determine the operational beam current.
  - Design collimator using GEANT4. Part of the collimator could be positioned inside the pressure vessel. At some point,
    Argonne ordered Cu material that could be available for us.
  • Test Schedule:
  - Start the Experiment Readiness Review process with a meeting with Arne and Rolf.