Line 8: | Line 8: | ||
* Plans: | * Plans: | ||
− | ** December: re-connect beamline magnet corrector | + | ** December: re-connect beamline magnet corrector; re-assemble TGun enclosure; PSS certification. |
− | ** January: | + | ** January: disconnect turbo and add pinch-off copper tube; beamline magnet racks and trim cards ON; Run 1 mA beam. |
* Beam Tests (if 1 mA run is successful): | * Beam Tests (if 1 mA run is successful): | ||
** TE011 cavity test | ** TE011 cavity test | ||
− | ** Vent gun HV chamber | + | ** Vent gun HV chamber; remove Kr line; re-activate cathode; ion trapping test. |
Latest revision as of 08:52, 16 December 2020
Work plan for December - January
- Notes:
- LERF is getting its own magnet power supply. We have GTS Gun Solenoid power supply from now on.
- Xelera is in no rush to take back TGun. Gun will stay at JLab as long as there is use for it.
- Plans:
- December: re-connect beamline magnet corrector; re-assemble TGun enclosure; PSS certification.
- January: disconnect turbo and add pinch-off copper tube; beamline magnet racks and trim cards ON; Run 1 mA beam.
- Beam Tests (if 1 mA run is successful):
- TE011 cavity test
- Vent gun HV chamber; remove Kr line; re-activate cathode; ion trapping test.