Difference between revisions of "2021-03-24"
Jump to navigation
Jump to search
(Created page with "== Meeting Information == ==== Connecting ==== To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST. # To join via a Web Browser, go to the pag...") |
|||
(4 intermediate revisions by the same user not shown) | |||
Line 13: | Line 13: | ||
==== <u>Schedule</u> ==== | ==== <u>Schedule</u> ==== | ||
Rough timetable: | Rough timetable: | ||
− | |||
# Beam studies until cryo transition to CMTF | # Beam studies until cryo transition to CMTF | ||
# PSS Certification immediately afterwards | # PSS Certification immediately afterwards | ||
Line 20: | Line 19: | ||
# Supplementary Shielding Installation: Mid-June | # Supplementary Shielding Installation: Mid-June | ||
# Beamline Commissioning / Test Plans / Shielding Verification: Late June / Early July | # Beamline Commissioning / Test Plans / Shielding Verification: Late June / Early July | ||
− | # | + | # Tentative (Pending Change request approval): Monday July 12th-Friday July 26th - Commission new beam line and execute experiment [May slide a week... and weekends also available if desired] |
− | |||
− | |||
==== <u>New items for discussion:</u> ==== | ==== <u>New items for discussion:</u> ==== | ||
− | * | + | * Target FSD update (hopefully!) |
− | + | * [[media:WastewaterIrradiation_McCaughan_long SAD change request.docx|Change request]] submitted to SAD Coordination Task Force - Under evaluation; they will discuss Thursday. (Mike) | |
− | * [[media:WastewaterIrradiation_McCaughan_long SAD change request.docx|Change request]] submitted to SAD Coordination Task Force - | ||
*#Once approved resource loaded schedule must be published internally for use | *#Once approved resource loaded schedule must be published internally for use | ||
− | * Beam Studies & Optics Characterization: Model development + Planned studies (John, Xi | + | * Gun heat and reactivation today (J. Grames executing) |
− | + | * Beam Studies & Optics Characterization: | |
− | * Engineering | + | *# Model development + Planned studies (John, Xi, Brian, Dennis) |
− | + | * Engineering | |
− | |||
* Other business | * Other business | ||
*#A formal run plan | *#A formal run plan |
Latest revision as of 07:56, 24 March 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Rough timetable:
- Beam studies until cryo transition to CMTF
- PSS Certification immediately afterwards
- CMTF tests with C75-1 (late-March - early-June). More refined CMTF schedule / testing duration?
- UITF beamline Modification in parallel to install new beamline
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification: Late June / Early July
- Tentative (Pending Change request approval): Monday July 12th-Friday July 26th - Commission new beam line and execute experiment [May slide a week... and weekends also available if desired]
New items for discussion:
- Target FSD update (hopefully!)
- Change request submitted to SAD Coordination Task Force - Under evaluation; they will discuss Thursday. (Mike)
- Once approved resource loaded schedule must be published internally for use
- Gun heat and reactivation today (J. Grames executing)
- Beam Studies & Optics Characterization:
- Model development + Planned studies (John, Xi, Brian, Dennis)
- Engineering
- Other business
- A formal run plan