Difference between revisions of "2021-06-23"

From Ciswikidb
Jump to navigation Jump to search
 
(3 intermediate revisions by the same user not shown)
Line 26: Line 26:
 
* FC3 & FC4 now hooked up, with thanks to Pete!
 
* FC3 & FC4 now hooked up, with thanks to Pete!
 
* Procurement of shielding by FML in progress - no dates yet.
 
* Procurement of shielding by FML in progress - no dates yet.
 
<u>Still to do:</u>
 
* Corrector / Raster installation this Thursday / Friday.
 
* Build 80/20 support structure; Pb table components awaiting delivery. Hardware arrival for table 6/29. Assembly next Thursday/Friday.
 
* Install target mechanism
 
* Add Mu metal over bellows on wastewater line.
 
 
 
  
 
*Gun work progressing well:
 
*Gun work progressing well:
Line 42: Line 34:
 
*#*[https://logbooks.jlab.org/entry/3881088 Steel puck added for HV conditioning]
 
*#*[https://logbooks.jlab.org/entry/3881088 Steel puck added for HV conditioning]
 
*#*[https://logbooks.jlab.org/entry/3881090 Damaged and ill-fitting pucks being re-machined]
 
*#*[https://logbooks.jlab.org/entry/3881090 Damaged and ill-fitting pucks being re-machined]
 +
*# [https://logbooks.jlab.org/entry/3881584 Anode and Cathode alignment completed in clean room by S&A]
 
*# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule]
 
*# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule]
 +
 +
<u>Still to do:</u>
 +
* Corrector / Raster installation this Thursday / Friday.
 +
* Build 80/20 support structure; Pb table components awaiting delivery. Hardware arrival for table 6/29. Assembly next Thursday/Friday.
 +
* Install target mechanism
 +
* Add Mu metal over bellows on wastewater line.
  
  
Line 62: Line 61:
 
==== <u>Reports on Open Action Items:</u> ====
 
==== <u>Reports on Open Action Items:</u> ====
 
Action Items:
 
Action Items:
*Formal run plan (McCaughan)
+
*Formal run plan (McCaughan) [[media:WWcommissioning.xlsx| Strawman]]
  
 
[[Meeting_minutes | Back to Main Meeting Minutes Page]]
 
[[Meeting_minutes | Back to Main Meeting Minutes Page]]

Latest revision as of 12:21, 23 June 2021

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
  3. To join via phone, use one of the following numbers and the Conference ID: 946721076.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. Supplementary Shielding Installation: ???
  2. Beamline Commissioning / Test Plans / Shielding Verification
  3. 7/26/21 Start Hot Check-out
  4. Commission new beam line and execute experiment
  5. Science!!!

New items for discussion:

Short term schedule update:
This week:

  • Vacuum work complete & leak checked. Thin window installed. All vacuum pumps are back on house power with all turbo pumps now detached. (With many thanks to Matt & John!!!) We should still consider preparing a back-up in case of rupture.
  • Survey and Alignment of the newly installed beam line completed
  • FC3 & FC4 now hooked up, with thanks to Pete!
  • Procurement of shielding by FML in progress - no dates yet.

Still to do:

  • Corrector / Raster installation this Thursday / Friday.
  • Build 80/20 support structure; Pb table components awaiting delivery. Hardware arrival for table 6/29. Assembly next Thursday/Friday.
  • Install target mechanism
  • Add Mu metal over bellows on wastewater line.


Next Week:

  • EES may start cabling downstream section & making UED updates.
  • Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
  • Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
  • Unistrut mounting for cables - Neal will do when available
  • Engineering work on beam line starting

2 weeks:

  • Pull Heliax from Spectrum analyzer/Control room >> Buncher
  • 4th terminal system in Control room under assembly/rebuild
  • Items from To-do list...

Engineering Other business

Reports on Open Action Items:

Action Items:

Back to Main Meeting Minutes Page