Difference between revisions of "2021-08-04"
Jump to navigation
Jump to search
(→Agenda) |
|||
(21 intermediate revisions by the same user not shown) | |||
Line 12: | Line 12: | ||
== Agenda == | == Agenda == | ||
==== <u>Schedule</u> ==== | ==== <u>Schedule</u> ==== | ||
− | Long Term Schedule: [[ | + | [[media:UITF-to-do-list8_4_21.docx| Comments from Matt]] |
+ | |||
+ | Long Term Schedule: [[media:WWinstall-8.4.21.pdf|Gantt]] ([[media:WWinstall-Todo_8.4.21.pdf|Outstanding tasks]]) | ||
# 8/9/21 Start Hot Check-out | # 8/9/21 Start Hot Check-out | ||
+ | # 8/16/21 Start commissioning (2 weeks) | ||
+ | # 8/30/21 Perform experiment (2 weeks) | ||
+ | # Booster qualification following experiment until cryo trade to CMTF | ||
==== <u>New items for discussion:</u> ==== | ==== <u>New items for discussion:</u> ==== | ||
− | + | '''General:''' | |
− | + | * [[UITF_Operations| Updated Ops Page]] | |
− | + | * [[media:WWcommissioning_2.xlsx| Commissioning plan (basic)]] | |
− | + | * [[Wastewater_Experiment_Commissioning_Plan| Commissioning plan (detailed, to break into shift plans)]] | |
− | |||
− | General: | ||
− | [[UITF_Operations| Updated Ops Page]] | ||
+ | ==== <u>'''Reports by Group:'''</u> ==== | ||
− | [[E-beam_Irradiation_Experiment| Experiment]]: | + | '''[[E-beam_Irradiation_Experiment| Experiment]]:''' |
* Past Experiment (HDIce) off floor largely; dilution refrigerator / pump cart craned out & high bay control room reconfigured for High-B. (With many thanks to install group for roofing tile gyrations!) | * Past Experiment (HDIce) off floor largely; dilution refrigerator / pump cart craned out & high bay control room reconfigured for High-B. (With many thanks to install group for roofing tile gyrations!) | ||
* Elevated beam line decommissioned upstream of M901 quad and terminated in roughing valve. | * Elevated beam line decommissioned upstream of M901 quad and terminated in roughing valve. | ||
* [[UE-21-001_Experimental_Binder_Documents| COO/ESAD/RSAD prepared]]; committee response in progress. | * [[UE-21-001_Experimental_Binder_Documents| COO/ESAD/RSAD prepared]]; committee response in progress. | ||
* Control room reconfigured | * Control room reconfigured | ||
+ | * Pull Heliax from Spectrum analyzer/Control room >> Buncher for beam study | ||
− | CIS/EGG: | + | '''CIS/EGG:''' |
* [https://logbooks.jlab.org/entry/3890263 Gun operating] at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!) | * [https://logbooks.jlab.org/entry/3890263 Gun operating] at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!) | ||
* Many improvements and modifications made to prep chamber. New pucks prepared as well. | * Many improvements and modifications made to prep chamber. New pucks prepared as well. | ||
Line 44: | Line 48: | ||
− | DC Power: | + | '''DC Power:''' |
*Trims: | *Trims: | ||
*# [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. | *# [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. | ||
Line 56: | Line 60: | ||
− | Instrumentation and Controls: | + | '''Instrumentation and Controls:''' |
− | |||
− | ''Viewer system status [IC; Norris / McCaughan]'' | + | ''Viewer system status [IC; Norris/Vennekate/McCaughan]'' |
− | * | + | * Recable 2 viewers in keV whose channels & hardware were appropriated for HDice (done) |
− | * | + | * Reconnect IYGM401 (formerly ITV, now YAG) |
− | * | + | * Drag cable and connect IYGM603 and IYGM603 (appropriated from HDice line, swapped ITV > YAG). |
− | * | + | * Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required... |
− | ''Wire Scanners [Delacruz / Poelker]'' | + | ''Wire Scanners [Delacruz/Poelker]'' |
* IHAM703 Status (Scanner swapped out) | * IHAM703 Status (Scanner swapped out) | ||
Line 72: | Line 75: | ||
''Chopper Controls (Windham/Lu)'' | ''Chopper Controls (Windham/Lu)'' | ||
* STAC5 Controls replacement (done) | * STAC5 Controls replacement (done) | ||
− | * Encoder mapping (/10) | + | * Encoder mapping (divide steps /10 over last controller) |
* Controls transparent to user | * Controls transparent to user | ||
Line 95: | Line 98: | ||
− | Vacuum | + | ''Vacuum (Ketchum/Kortze)'' |
* VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation. | * VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation. | ||
* VFVM401 Fast Valve installation | * VFVM401 Fast Valve installation | ||
Line 102: | Line 105: | ||
* Numerous VIPs installed, functional, on EPICS, and archived. | * Numerous VIPs installed, functional, on EPICS, and archived. | ||
* Thin Ti window installed by experiment, pumped down, leak checked , and signage / PPE posted. | * Thin Ti window installed by experiment, pumped down, leak checked , and signage / PPE posted. | ||
− | |||
− | |||
Line 110: | Line 111: | ||
− | RF: | + | '''RF:''' |
− | + | * [https://logbooks.jlab.org/entry/3885411 6GHz] > 1.5GHz Down-converter installed for bunch length system | |
+ | * LLRF 2.0 FCC for reading signal | ||
+ | * Laser RF HCO | ||
+ | |||
+ | '''SSG:''' | ||
− | + | ''BLM installation underway:'' | |
− | # | + | * Replace those previously removed |
− | # FSD inputs | + | * Additions |
+ | *# In crotch of MeV/Wastewater selecting dipole. | ||
+ | *# Near 1st new diagnostic cross d.s. of solenoid | ||
+ | *# Near 2nd new diagnostic cross by FC4 | ||
+ | *# D.S. of target after lead shielding | ||
+ | ''FSD inputs (original)'' | ||
+ | * Target motion (now software interlock) | ||
+ | * Solenoid (Now engineered control) | ||
+ | * BCM current clamp system | ||
+ | * Update gold masking | ||
− | ME / Installation: | + | '''ME / Installation:''' |
− | + | * Pb stacked; RCG required modification due to permanent shielding req delay. | |
− | + | * New designs for [[media:FC3-SHIELDING_20JUL21v1.pdf|FC3]] and [[media:FC4-SHIELDING_20JUL21v1.pdf|FC4]] with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction! | |
− | + | * [[media:JL0029599-2000UITF_MeV_BEAMLINE07-JUN-21.pdf|Songsheet]] being updated by Shaun; be sure to let him know when changes are made! | |
− | + | * Permanent shielding purchase in progress - FML (Russ) for most current details | |
− | + | * Unistrut mounting for cables when available | |
− | + | * Mount [https://logbooks.jlab.org/entry/3877442 gas bottle rack] in Labyrinth (Staged); remove gas bottles to rack. | |
− | Sys Admin: | + | '''Sys Admin:''' |
* 4th terminal system in Control room under assembled/rebuilt | * 4th terminal system in Control room under assembled/rebuilt | ||
* Wall server configured | * Wall server configured | ||
Line 134: | Line 148: | ||
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | * [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
[[Meeting_minutes | Back to Main Meeting Minutes Page]] | [[Meeting_minutes | Back to Main Meeting Minutes Page]] |
Latest revision as of 12:29, 4 August 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
- To join via phone, use one of the following numbers and the Conference ID: 984025598.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- 8/9/21 Start Hot Check-out
- 8/16/21 Start commissioning (2 weeks)
- 8/30/21 Perform experiment (2 weeks)
- Booster qualification following experiment until cryo trade to CMTF
New items for discussion:
General:
- Updated Ops Page
- Commissioning plan (basic)
- Commissioning plan (detailed, to break into shift plans)
Reports by Group:
- Past Experiment (HDIce) off floor largely; dilution refrigerator / pump cart craned out & high bay control room reconfigured for High-B. (With many thanks to install group for roofing tile gyrations!)
- Elevated beam line decommissioned upstream of M901 quad and terminated in roughing valve.
- COO/ESAD/RSAD prepared; committee response in progress.
- Control room reconfigured
- Pull Heliax from Spectrum analyzer/Control room >> Buncher for beam study
CIS/EGG:
- Gun operating at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!)
- Many improvements and modifications made to prep chamber. New pucks prepared as well.
- HV tests with a GaAs puck (#8) in the gun (8/3) [Carlos]
- Gun HVPS locked out , reconnect gun valve, charge NF3, degas heater/puck, get UITF laser on (8/4)
- Make photocathode (8/5) [Joe/Max]
- Align laser to photocathode, using retro and QE (8/5) [Shukui]
- Gun rebuild wiki
- Racks and Mott crate staged for later experiments
Old insulator (punctured) & Old puck manipulator/schneedle for reference; both replaced. Very modest SF6 leak id-ed on top of HV tank; will repair when practical.
DC Power:
- Trims:
- Trim magnets near gun re-cabled.
- Wastewater beam line trims cabled up.
- Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad
- Former PEPPo solenoid repaired, mapped, and installed.
- Solenoid PS being installed. Supply placed, cables pulled, cabled, and LCW hooked up.
- MHB magnet re-designation to MLH to avoid confusion: Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets
- Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
- Replacement of cards and utility chassis' acquired for CEBAF under way...
Instrumentation and Controls:
Viewer system status [IC; Norris/Vennekate/McCaughan]
- Recable 2 viewers in keV whose channels & hardware were appropriated for HDice (done)
- Reconnect IYGM401 (formerly ITV, now YAG)
- Drag cable and connect IYGM603 and IYGM603 (appropriated from HDice line, swapped ITV > YAG).
- Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required...
Wire Scanners [Delacruz/Poelker]
- IHAM703 Status (Scanner swapped out)
Chopper Controls (Windham/Lu)
- STAC5 Controls replacement (done)
- Encoder mapping (divide steps /10 over last controller)
- Controls transparent to user
Chopper Controls (Windham/Lu)
- Target Motion Control - Carriage remotely operable, step count needs some fine tuning.
- Control Screen complete?
BPMs (Windham / Hesse / McCaughan)
- Install new BPMs on line (completed)
- Map DR receivers to appropriate chassis (completed)
- Correct all naming and controls issues
- Re-label locally.
Faraday Cups / Picoammeters (Francis)
- FC cups 3 & 4 installed in new locations and under vacuum
- Cables / air lines /etc pulled to new locations and installed
- Connections removed for shielding installation per RCG.
- Picoammeters all good - some screen work required.
Vacuum (Ketchum/Kortze)
- VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation.
- VFVM401 Fast Valve installation
- VCGM604 Cathode Gauge installed
- VGPM401, 603, 604, and 703 NEG pumps - installation completed, activated, status of remote powering?
- Numerous VIPs installed, functional, on EPICS, and archived.
- Thin Ti window installed by experiment, pumped down, leak checked , and signage / PPE posted.
BCM
- BCM project software integration under way between Musson/Seaton and Sue Witherspoon
RF:
- 6GHz > 1.5GHz Down-converter installed for bunch length system
- LLRF 2.0 FCC for reading signal
- Laser RF HCO
SSG:
BLM installation underway:
- Replace those previously removed
- Additions
- In crotch of MeV/Wastewater selecting dipole.
- Near 1st new diagnostic cross d.s. of solenoid
- Near 2nd new diagnostic cross by FC4
- D.S. of target after lead shielding
FSD inputs (original)
- Target motion (now software interlock)
- Solenoid (Now engineered control)
- BCM current clamp system
- Update gold masking
ME / Installation:
- Pb stacked; RCG required modification due to permanent shielding req delay.
- New designs for FC3 and FC4 with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction!
- Songsheet being updated by Shaun; be sure to let him know when changes are made!
- Permanent shielding purchase in progress - FML (Russ) for most current details
- Unistrut mounting for cables when available
- Mount gas bottle rack in Labyrinth (Staged); remove gas bottles to rack.
Sys Admin:
- 4th terminal system in Control room under assembled/rebuilt
- Wall server configured
- Need to configure wall monitors and install small networked printer.