== Recent Updates ==
+
==Useful Links==
 +
* Zoom => Daily 8:00am + Wed 1:30 MCC => https://jlab-org.zoomgov.com/j/1601304841?pwd=Z1RIOVVUdkdXL2R2LzREZUNOUlh1dz09
 +
* Zoom => Daily 8:30am (or when 8am ends) Injector Toolbox meeting => https://jlab-org.zoomgov.com/j/1605740081?pwd=ZWxFREIyVmFtbW04VGZ4M1Jia3JrZz09&from=addon
 +
* [[Running Daily Phase 2 Minutes]]
 +
* [[https://jeffersonlab-my.sharepoint.com/:x:/g/personal/marcy_jlab_org/EUe-xbLpNR1IsV28fyi20FUBgR_iWPHI2jAfsc9wJE00oQ?e=Wmp1Mr&CID=9ace3d4c-3c26-a771-e9b4-3e5d57e60bc9 Marcy's Gantt]]
  
*  
+
== CIS coordinators ==
 +
Attends 8am meeting(s), join the 8:30am zoom afterwards...
 +
* 3/20 - 4/3: Joe
 +
: Matt's first two weeks plan => [[media:Matts_SAD 2023_injector_weeks_1_2.docx]]
 +
: Move gun table back and forth => [[media:Gun-Table-Move.pptx]]
 +
* 4/3 - 4/17: Carlos
 +
* 4/17 - 5/1: Marcy
 +
* 5/1 -  5/15: Riad
  
==Planning, planning, planning...==
+
== Main Areas ==
* [[AIPINJ - Phase 2 Upgrade Meetings]]
 
* [[AIPINJ - Phase 2 Layouts]]
 
  
== Major Phase 2 Beamline Components ==
+
: [[200 kV Polarized Gun]]
:[[SRF Booster]]
+
: [[SRF Booster]]
:[[media:parts list old and new phase2 beamline.xls]]
+
: [[Phase 2 info just at end of Phase 1]]
 +
: Yan's commissioning plan => [[media:Yans_Commissioning of Injector upgrade II-1.docx]]
  
==FY22 SAD ATLIS Tasks==
+
== Beam Commissioning ATLIS Jobs ==
 
+
* Viewer perspectives (6/21/21) here => [https://wiki.jlab.org/ciswiki/index.php/Beamline_viewers 3d CAD images of the viewers]
===Schedule===
+
* (Max) Test IHA0I02 after SAD - https://tasklists.jlab.org/bslist/tasks/108546
* CEBAF SAD runs from Feb 8 - Jun 8 (about 4 months) [[media:210112_SAD_timeline.pdf]]
+
* (Max) 200 kV gun optics and 2I steering - https://tasklists.jlab.org/bslist/tasks/108544
* Jason Willoughby is installing bright white task lighting w/ wall dimmer from laser hut to fc#2
+
* (Max & Dennis) 200 keV Wien filter optics
* Install group may remove 5D line in prep for Phase 2 https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22161
+
** https://tasklists.jlab.org/bslist/tasks/108547
* Tunnel jobs during first ~month of SAD
+
** https://tasklists.jlab.org/bslist/tasks/107364
:: Tomasz is upgrading RF https://opsweb.acc.jlab.org/CSUEApps/atlis/task/21376
+
* (Riad) Wien E/B and spin calibrations
:: CIS has two major vacuum jobs
+
** https://tasklists.jlab.org/bslist/tasks/108388
* Beam base jobs follow, accomodating PSS
+
** https://tasklists.jlab.org/bslist/tasks/108389
 
 
=== Vent VBV0I02 - VBV0I07 ===
 
* Marcy write ATLIS
 
* Coordinate groups to remove/stow items
 
* Coordinate with SRF before venting
 
* Dry run the entire sequence of jobs
 
* Prep all the parts for vacuum job in tunnel
 
* Vent through QCM
 
* Work w/ S&A to remake A2 gasket
 
* Rework IYG0I02, remove top-hat, align YAG screen per Dennis
 
* Work with S&A to align YAG screen
 
* Work with S&A to install, align IHA0I02
 
* Check viewer and harp before and after pump down, repeatedly, carefully
 
* Pump down and leak check
 
 
 
=== Vent Mott chamber  ===
 
* Joe write ATLIS
 
* Coordinate with S&A to check gold ladder fiducials
 
* Coordinate with Scott to disconnect diamond ladder controls
 
* Dry run the entire sequence in tunnel
 
* Prep all the parts before venting
 
* Vent chamber slowly for existing gold target
 
* Remove diamond ladder
 
* Rebuild lower section of Mott (tube + window)
 
* Last step install and align gold ladder
 
* Slow pump down, check motion controls of ladder, leak check
 
* Long pump down
 
 
 
=== Beam Based Tests ===
 
* (Shukui, Joe, Tomasz, Reza) Install and test mode locked fiber laser https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22830
 
* (Dennis, Ken, Alicia) Use harp to study Wien optics and test match
 
* (Dennis) Evaluate optics of Lakshmi's new 15 deg DM dipole vs. existing DS dipole
 
* (Max) Use BPM, Harp/lens to quantify beam deflection & Twiss vs. laser spot location
 
* (Riad, Sarin) Use BPM's and Wiens to test different/new PS to suppress line noise
 
* (Gabriel, Carlos) Do you need data for Wien paper?
 
* (Jerry, Joe) Test 200 keV PSS kicker magnet https://opsweb.acc.jlab.org/CSUEApps/atlis/task/22061
 
* (Yan) Evaluate QCM
 

Latest revision as of 11:43, 19 March 2023

Useful Links

CIS coordinators

Attends 8am meeting(s), join the 8:30am zoom afterwards...

  • 3/20 - 4/3: Joe
Matt's first two weeks plan => media:Matts_SAD 2023_injector_weeks_1_2.docx
Move gun table back and forth => media:Gun-Table-Move.pptx
  • 4/3 - 4/17: Carlos
  • 4/17 - 5/1: Marcy
  • 5/1 - 5/15: Riad

Main Areas

200 kV Polarized Gun
SRF Booster
Phase 2 info just at end of Phase 1
Yan's commissioning plan => media:Yans_Commissioning of Injector upgrade II-1.docx

Beam Commissioning ATLIS Jobs