Difference between revisions of "Meeting 6/29/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
 
(12 intermediate revisions by the same user not shown)
Line 1: Line 1:
6/23/22 Minutes
+
; Thursday's @ 9am EDT by Zoom
 +
* Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
 +
* Zoom ID: 160 190 6056 and Passcode: 992019
 +
* Meeting wiki - https://wiki.jlab.org/ciswiki/index.php/Meeting_6/29/22_-_COMTRA
 +
 
 +
===6/30/22 Updates...===
  
 
;ME
 
;ME
* Stands - Last week we said 'pull the trigger' on UITF stand (has been purchased?), later will order stand for BNL
+
* Stands - Last week we said 'pull the trigger' on UITF stand (has been purchased?), later will order stand for BNL => '''Where is PR?'''
 
* Collimator - Last week Riad provided drawing, found material but does not know if OHFC.  Need (2) per this drawing.  [[media:JL0015777_Cu_collimator.pdf]]  '''What about ID hole???'''  
 
* Collimator - Last week Riad provided drawing, found material but does not know if OHFC.  Need (2) per this drawing.  [[media:JL0015777_Cu_collimator.pdf]]  '''What about ID hole???'''  
 
* Absorbers - Christine provided drawing 6/3, I forgot to act on this!  Need (6) per this drawing => [[media:Absorber - 240 D 001 14_V4.pdf]]
 
* Absorbers - Christine provided drawing 6/3, I forgot to act on this!  Need (6) per this drawing => [[media:Absorber - 240 D 001 14_V4.pdf]]
Line 9: Line 14:
 
* Power supply with ethernet and rack mount option - PR 6/9, PO 6/13, request 6/24 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
 
* Power supply with ethernet and rack mount option - PR 6/9, PO 6/13, request 6/24 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
 
* Magnet winding around JLab machined cores - PR 5/31, PO 6/2, request 7/15 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
 
* Magnet winding around JLab machined cores - PR 5/31, PO 6/2, request 7/15 => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
 +
* Model development => 6/27 Probir provided magnetic model to Greg.  Eric, can you outline how we used magnet model for PEPPo AM in Geant (to assign B-field in air/magnet, P-field in iron core)?
  
 
;Detector
 
;Detector
* BGO crystals - Arrived in Richmond, Deringer controls paperwork, 6/28 proceeding for ground DHL to JLab date
+
* BGO crystals - 6/28 - Arrived in Richmond, Deringer controls paperwork, 6/29 - DHL delivery due at JLab
 
* PMT status - (4) Hamamatsu tubes w/ magnetic shield, PR 6/1, PO 6/2, due 8/2 or earlier => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
 
* PMT status - (4) Hamamatsu tubes w/ magnetic shield, PR 6/1, PO 6/2, due 8/2 or earlier => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
 
* PMT base status?
 
* PMT base status?
Line 18: Line 24:
 
;DAQ
 
;DAQ
 
* PMT-5R ItoV amplifier with remote control - 6/23 CC order placed to Advanced Instruments Corp, delivery date TBD
 
* PMT-5R ItoV amplifier with remote control - 6/23 CC order placed to Advanced Instruments Corp, delivery date TBD
 +
* Rack- Last week? we discussed a rack layout showing all components + add/list odds/ends still needed UITF cables, connectors, patch panel, lifting bolts?, wheels?, can we finalize/order these
 +
* Rest of DAQ (hardware and software) - how are we looking for UITF readiness ... Like = Aug 1, Should = Sep 1, Must = Oct 1
 +
 +
;Documentation
 +
* NIM paper - 6/29 created overleaf folder with Elsevier Article (elsarticle) template, will share after framing outline => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
 +
* Portable Compton Polarimeter Manual - Still TBD, ideas how to outline this one?  Do in Overleaf too, or is a Sharepoint Word file better for drag/drop, everyone, etc?
  
;What else?
+
;Greg's weekly meeting
* NIM paper - Riad's good idea - some of us will draft an outline in overleaf, later we'll look for short technical descriptions/results,
+
* Geant4 simulations - Joe/Eric/Riad ? and when ?
* Manual - More of an operational document to augment NIM paper technical description
 

Latest revision as of 14:21, 29 June 2022

Thursday's @ 9am EDT by Zoom

6/30/22 Updates...

ME
  • Stands - Last week we said 'pull the trigger' on UITF stand (has been purchased?), later will order stand for BNL => Where is PR?
  • Collimator - Last week Riad provided drawing, found material but does not know if OHFC. Need (2) per this drawing. media:JL0015777_Cu_collimator.pdf What about ID hole???
  • Absorbers - Christine provided drawing 6/3, I forgot to act on this! Need (6) per this drawing => media:Absorber - 240 D 001 14_V4.pdf
Analyzing Magnet
Detector
  • BGO crystals - 6/28 - Arrived in Richmond, Deringer controls paperwork, 6/29 - DHL delivery due at JLab
  • PMT status - (4) Hamamatsu tubes w/ magnetic shield, PR 6/1, PO 6/2, due 8/2 or earlier => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
  • PMT base status?
  • Detector box status?
DAQ
  • PMT-5R ItoV amplifier with remote control - 6/23 CC order placed to Advanced Instruments Corp, delivery date TBD
  • Rack- Last week? we discussed a rack layout showing all components + add/list odds/ends still needed UITF cables, connectors, patch panel, lifting bolts?, wheels?, can we finalize/order these
  • Rest of DAQ (hardware and software) - how are we looking for UITF readiness ... Like = Aug 1, Should = Sep 1, Must = Oct 1
Documentation
  • NIM paper - 6/29 created overleaf folder with Elsevier Article (elsarticle) template, will share after framing outline => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
  • Portable Compton Polarimeter Manual - Still TBD, ideas how to outline this one? Do in Overleaf too, or is a Sharepoint Word file better for drag/drop, everyone, etc?
Greg's weekly meeting
  • Geant4 simulations - Joe/Eric/Riad ? and when ?