Difference between revisions of "Meeting 7/14/22 - COMTRA"
Jump to navigation
Jump to search
(4 intermediate revisions by one other user not shown) | |||
Line 23: | Line 23: | ||
* UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1 | * UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1 | ||
* BNL Stand - agreed w/ Cliff, will work up the order | * BNL Stand - agreed w/ Cliff, will work up the order | ||
− | * Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => Machine request in; copper cylinder provided | + | * Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => Machine Shop request in; copper cylinder provided |
− | * Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => Machine request in | + | * Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => Machine Shop request in [https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm;jsessionid=72888DCB6ACFE194CC116F841A221DB1.cfusion?request_id=331095&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11 Shop job] |
;Geant4 Model | ;Geant4 Model | ||
− | * Adding magnetic model | + | * Adding magnetic model: got only truncated field map |
− | * Simulation study (due 7/ | + | * Simulation study (due 7/21) |
;Documentation | ;Documentation | ||
* NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a | * NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a | ||
* Manual - Sharepoint | * Manual - Sharepoint |
Latest revision as of 15:30, 14 July 2022
- Thursday's @ 9am EDT by Zoom
- Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
- Zoom ID: 160 190 6056 and Passcode: 992019
- Meeting wiki - https://wiki.jlab.org/ciswiki/index.php/Meeting_7/14/22_-_COMTRA
7/14/22 Update
- Analyzing Magnet
- PS (new => week of Aug 8th) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
- Magnet (request 7/15) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
- DAQ & RACK
- PMT-5R ItoV amplifier (due TBD)
- To-do => final cable, connector, rack layout
- Detector
- BGO crystals - Arrived at JLab, stored in cabinet
- PMTs (due 8/2) => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
- PMT bases (due 8/1-9/15)
- Detector boxes (ship by 8/1)
- ME
- UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
- BNL Stand - agreed w/ Cliff, will work up the order
- Collimator - Fabricate (2) media:JL0015777_Cu_collimator.pdf => Machine Shop request in; copper cylinder provided
- Absorbers - Fabricate (6) media:Absorber - 240 D 001 14_V4.pdf => Machine Shop request in Shop job
- Geant4 Model
- Adding magnetic model: got only truncated field map
- Simulation study (due 7/21)
- Documentation
- NIM - Elsevier Article (elsarticle) template => https://www.overleaf.com/project/62bc9efe48a3a93aef37be0a
- Manual - Sharepoint