Difference between revisions of "Meeting 8/4/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
 
(13 intermediate revisions by the same user not shown)
Line 2: Line 2:
 
* Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
 
* Join ZoomGov Meeting - https://jlab-org.zoomgov.com/j/1601906056?pwd=V2xxUjJhQWN3RC91M2ZBOUVrbmhnUT09
 
* Zoom ID: 160 190 6056 and Passcode: 992019
 
* Zoom ID: 160 190 6056 and Passcode: 992019
 +
 +
===Schedule===
 +
* Installation jobs may begin as early as next week and must be completed by end of Sep
 +
* Run is planned for October exact dates TBD
 +
* We will share the run period with another MeV energy experiment
  
 
===Magnet===
 
===Magnet===
* Kepco PS -'''due week of Aug 8th''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
+
* Kepco PS - '''due 8/12''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
* Magnet - '''request 7/15''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
+
* Magnet - '''due 7/15''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
  
 
===DAQ ===
 
===DAQ ===
* PMT-5R ItoV - '''arrived'''
+
* PMT-5R ItoV - on-hand
* Cable pull from UITF control room to cave
+
* Cables - '''pull from control room to cave'''
  
 
===Detector===
 
===Detector===
* BGO crystals - '''arrived'''
+
* Collimator - (2) on-hand [[media:JL0015777_Cu_collimator.pdf]] [[File:IMG_20220804_082153706.jpg|thumb]]
* PMTs - '''arrived'''
+
* Absorbers - (6) on-hand [[media:Absorber - 240 D 001 14_V4.pdf]] [[File:IMG_20220804_082037794.jpg|thumb]]
* PMT bases - '''due 8/1-9/15'''
+
* Boxes - '''(2) shipped DHL, due 8/9'''
* Detector boxes - '''shipped DHL, est. del. 8/9'''
+
* BGO - (2) on-hand [[File:IMG_20220804_084436318.jpg|thumb]]
 +
* PMT - on-hand [[File:IMG_20220804_081738760.jpg|thumb]]
 +
* Bases - '''due 9/15'''
  
 
===Layout===
 
===Layout===
* New layout
+
* Beamline
** zero-length reducer 4.5 to 2.75 - still need?
+
** Radiator - (1) on-hand, '''(1) need for BNL''' [[File:IMG_20220804_084829378.jpg|thumb]]
** Spool 4.25 lg  [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
+
** ?? zero-length reducer 4.5 to 2.75  
 +
** ?? Spool 4.25 lg  [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
 
* Stands
 
* Stands
 
** UITF PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
 
** UITF PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
 
** * Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
** * Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
** BNL Stand - agreed w/ Cliff, will work up the order
 
** BNL Stand - agreed w/ Cliff, will work up the order
* UITF Lead
+
* Lead
** 2 X 4 X 4 – Need 11
+
** UITF - (11) 2 X 4 X 4, (2) 2 X 4 X 6, (99) 2 X 4 X 8 [[File:IMG_20220804_084121573.jpg|thumb]]
** 2 X 4 X 6 – Need 2
 
** 2 X 4 X 8 – Need 99
 
* Radiator - '''(1) on-hand, (1) need for BNL'''
 
* Collimator - '''(2) completed''' [[media:JL0015777_Cu_collimator.pdf]]
 
* Absorbers - '''(6) completed''' [[media:Absorber - 240 D 001 14_V4.pdf]]
 
  
 
===Geant4 Model===
 
===Geant4 Model===

Latest revision as of 07:56, 4 August 2022

Thursday's @ 9am EDT by Zoom

Schedule

  • Installation jobs may begin as early as next week and must be completed by end of Sep
  • Run is planned for October exact dates TBD
  • We will share the run period with another MeV energy experiment

Magnet

DAQ

  • PMT-5R ItoV - on-hand
  • Cables - pull from control room to cave

Detector

Layout

Geant4 Model

Documentation