− | + | Wednesday September 30 @ 2pm in Bldg. 87 Rm. 101 | |
− | + | Arne's priorities: Nov. 9th the following things MUST be accomplished. | |
− | + | # CW beam to the inline dump 85uA from A laser, 1uA from the D laser | |
+ | # Wien setup for alignment of polarization to Hall-A on 5-pass | ||
+ | # Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6 | ||
+ | # Beam matched in the inj. chicane, ready for transport into the NL. | ||
+ | # All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane | ||
+ | # RF calibration tool fully developed (anticipate Nov. 2-7 DAYS) | ||
+ | # quad centering tool fully developed (anticipate Nov. 2-7 DAYS) | ||
− | + | Injector Tests and Calendar [[media:150929_InjectorTestList.xlsx]] [[media:150929_InjectorTestList.pdf]] | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | + | [https://devweb.acc.jlab.org/twiki/bin/view/BTeam/BTeam20150922 September 22, 2015 B-Team notes for Fall startup] | |
− | |||
− |
Latest revision as of 11:33, 30 September 2015
Wednesday September 30 @ 2pm in Bldg. 87 Rm. 101
Arne's priorities: Nov. 9th the following things MUST be accomplished.
- CW beam to the inline dump 85uA from A laser, 1uA from the D laser
- Wien setup for alignment of polarization to Hall-A on 5-pass
- Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6
- Beam matched in the inj. chicane, ready for transport into the NL.
- All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane
- RF calibration tool fully developed (anticipate Nov. 2-7 DAYS)
- quad centering tool fully developed (anticipate Nov. 2-7 DAYS)
Injector Tests and Calendar media:150929_InjectorTestList.xlsx media:150929_InjectorTestList.pdf