(Created page with "===200kV Gun=== * Timeline/sequence for 200kV HV chamber ===Gun2 NEG Tube=== * Danny updated NEG tube media:NEGTUBE_MARCH31.pdf ===Gun3 Removal=== * Week May 8 to remove...") |
|||
Line 15: | Line 15: | ||
===Radmon update=== | ===Radmon update=== | ||
+ | * Omar will NOT be ready w/ new system => plan on borrowing from LERF (or GTS?) | ||
===SAD Schedule=== | ===SAD Schedule=== | ||
* [https://accweb.acc.jlab.org/calendar/ SAD Calendar] | * [https://accweb.acc.jlab.org/calendar/ SAD Calendar] |
Revision as of 20:16, 12 April 2017
200kV Gun
- Timeline/sequence for 200kV HV chamber
Gun2 NEG Tube
- Danny updated NEG tube media:NEGTUBE_MARCH31.pdf
Gun3 Removal
- Week May 8 to remove/replace Gun3 ATLIS task
Eliminating Gun Switch Software
- Kyle building a new screen, tracking to be ready in May or June
Spellman HVPS update
- John/Brad can now talk to HVPS
Radmon update
- Omar will NOT be ready w/ new system => plan on borrowing from LERF (or GTS?)