Difference between revisions of "UITF Meeting - June 15, 2018"
Jump to navigation
Jump to search
(Created page with " ---- Tasks before running beam to HDIce for target commissioning ---- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and compan...") |
|||
Line 6: | Line 6: | ||
− | Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company) | + | # Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company) |
− | + | # Vacuum Group, build the MeV beamline | |
− | + | # Cryo: install the helium return line | |
− | + | # SRF, need a point of contact for all things related to QCM operation | |
− | + | # Electrical engineering: design and build the PSS BCM | |
− | + | # Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today) | |
− | + | # Magnet group: give us a third trim card rack | |
− | + | # RF group: klystrons, high power amplifier, solid state amp, water skids | |
− | + | # Vashek: finish specifying the shielding requirements, then we start moving lead | |
− | + | # R&D related to low current BPMs, suggest you take that on, with help from Engineering | |
− | + | # Operations Group should augment Joe's modeling, using a particle tracking code | |
− | + | # Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review | |
− | + | # Gun group needs to build a new photogun | |
− | + | # Need to operate the UITF on a daily basis..... |
Revision as of 12:37, 13 June 2018
Tasks before running beam to HDIce for target commissioning
- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
- Vacuum Group, build the MeV beamline
- Cryo: install the helium return line
- SRF, need a point of contact for all things related to QCM operation
- Electrical engineering: design and build the PSS BCM
- Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
- Magnet group: give us a third trim card rack
- RF group: klystrons, high power amplifier, solid state amp, water skids
- Vashek: finish specifying the shielding requirements, then we start moving lead
- R&D related to low current BPMs, suggest you take that on, with help from Engineering
- Operations Group should augment Joe's modeling, using a particle tracking code
- Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
- Gun group needs to build a new photogun
- Need to operate the UITF on a daily basis.....