Difference between revisions of "Summer SAD 2019"
Jump to navigation
Jump to search
Line 11: | Line 11: | ||
[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19463 Upgrade the loading chamber] | [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19463 Upgrade the loading chamber] | ||
− | + | [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19465 Upgrade fiber laser connectors] | |
Carlos will write an ATLIS to HV process the gun | Carlos will write an ATLIS to HV process the gun | ||
Joe will write an ATLIS to run 200 keV beam | Joe will write an ATLIS to run 200 keV beam |
Revision as of 11:54, 15 July 2019
- Gun upgrades for Summer SAD 2019
media:190501_GunUpgradeJobs.docx
Gun2 Load Lock Chamber Replacement
- ATLIS tasks
Gun2 200kV cathode, 10kV anode, kr plumbing
Upgrade fiber laser connectors
Carlos will write an ATLIS to HV process the gun
Joe will write an ATLIS to run 200 keV beam