Difference between revisions of "January 13, 2020 - Service providers"
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
* Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD. | * Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD. | ||
* During the 2020 SAD we will... | * During the 2020 SAD we will... | ||
− | :-Make the gun operate a 200 kV | + | :-Make the gun operate a 200 kV (A: make present gun operate 200 kV, B: install new electrode) |
:-Reconfigure beam line extending from gun through chopper | :-Reconfigure beam line extending from gun through chopper | ||
:-Commission the new gun and beam line with 200 keV beam | :-Commission the new gun and beam line with 200 keV beam | ||
Line 12: | Line 12: | ||
:-This means the capture and QCM remain until Booster installed | :-This means the capture and QCM remain until Booster installed | ||
:-This also means we'll operate the gun and beam line at 130 keV until that time too | :-This also means we'll operate the gun and beam line at 130 keV until that time too | ||
+ | |||
+ | ===Status of the 2020 beam line upgrade=== | ||
+ | * Layout | ||
+ | :-We have a preliminary ME layout, mainly to tally that everything will fit; notably we have a pretty good idea what everything will be | ||
+ | :-CIS/INJ/CASA are evaluating exact sequence for functionality and to model the envelope, aiming to have this pretty well defined in Feb | ||
+ | * On the topic of everything, how does this go: | ||
+ | :Magnets | ||
+ | ::-Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround | ||
+ | ::-Wien filters, PO written, coils due early march | ||
+ | ::-15 deg dipole, bids received, anticipate PO within a ~week | ||
+ | ::-steering coils, should have enough in hand, will order spares once layout done | ||
+ | ::-Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially |
Revision as of 10:36, 13 January 2020
Service providers discussion
Scope of 2020 SAD
- Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
- During the 2020 SAD we will...
- -Make the gun operate a 200 kV (A: make present gun operate 200 kV, B: install new electrode)
- -Reconfigure beam line extending from gun through chopper
- -Commission the new gun and beam line with 200 keV beam
Beyond 2020 SAD
- We will not modify the configuration downstream of chopper until new Booster goes in
- -This means the capture and QCM remain until Booster installed
- -This also means we'll operate the gun and beam line at 130 keV until that time too
Status of the 2020 beam line upgrade
- Layout
- -We have a preliminary ME layout, mainly to tally that everything will fit; notably we have a pretty good idea what everything will be
- -CIS/INJ/CASA are evaluating exact sequence for functionality and to model the envelope, aiming to have this pretty well defined in Feb
- On the topic of everything, how does this go:
- Magnets
- -Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround
- -Wien filters, PO written, coils due early march
- -15 deg dipole, bids received, anticipate PO within a ~week
- -steering coils, should have enough in hand, will order spares once layout done
- -Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially