Difference between revisions of "NEG coated 2.5 inch OD BPM's"

From Ciswikidb
Jump to navigation Jump to search
Line 4: Line 4:
 
*weldment [[media:JL0091130-0114 BPM TUBE WELDMENT, REV-.pdf]]
 
*weldment [[media:JL0091130-0114 BPM TUBE WELDMENT, REV-.pdf]]
  
 
+
== Assembly Sequence ==
== Gabou Measurements ==
 
 
 
* NEG BPM #1
 
* NEG BPM #2
 
* NEG BPM #3
 
* NEG BPM #4
 
 
 
== Assembly ==
 
;Assembly sequence
 
 
# Receive can/feedthroughs
 
# Receive can/feedthroughs
 
# Clean
 
# Clean
Line 24: Line 15:
 
# electrical measurement
 
# electrical measurement
 
# report K's and center
 
# report K's and center
 +
 +
== Gabou Measurements ==
 +
 +
* Summary - [[media:UITF_SPM_Summary_9_21.ods]]
 +
 +
* NEG BPM #1
 +
::- [[media:NEG_1_1cmx2cm_lower.pdf]]
 +
* NEG BPM #2
 +
::- [[media:NEG_2_1cmx2cm_upper.pdf]]
 +
::- [[media:NEG_2_1cmx2cm_boresight.pdf]]
 +
* NEG BPM #3
 +
* NEG BPM #4

Revision as of 16:11, 14 June 2021

New BPM's were developed for the 200 kV gun NEG tube beam line.

ME Design

Assembly Sequence

  1. Receive can/feedthroughs
  2. Clean
  3. Degas
  4. NEG Coat
  5. Check feedthroughs
  6. Assemble feedthroughs
  7. serialize
  8. Leak check cans
  9. electrical measurement
  10. report K's and center