Difference between revisions of "2021-07-21"

From Ciswikidb
Jump to navigation Jump to search
Line 5: Line 5:
 
To connect to the meeting, please do the following:
 
To connect to the meeting, please do the following:
 
Time: Wednesday at 9:00 AM EST.
 
Time: Wednesday at 9:00 AM EST.
# To join via a Web Browser, go to the page [https://bluejeans.com/946721076] https://bluejeans.com/946721076.
+
# To join via a Web Browser, go to the page [https://bluejeans.com/984025598] https://bluejeans.com/984025598.
# To join via Polycom room system go to the IP Address: 199.48.152.152 ([http://bjn.vc bjn.vc]) and enter the meeting ID: 946721076.
+
# To join via Polycom room system go to the IP Address: 199.48.152.152 ([http://bjn.vc bjn.vc]) and enter the meeting ID: 984025598.
# To join via phone, use one of the following numbers and the Conference ID: 946721076.
+
# To join via phone, use one of the following numbers and the Conference ID: 984025598.
 
#* Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
 
#* Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
  

Revision as of 07:04, 21 July 2021

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
  3. To join via phone, use one of the following numbers and the Conference ID: 984025598.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. 7/26/21 Start Hot Check-out


New items for discussion:

Short term schedule update:
This week:

Gun work progressing well:

Still to do:

  • Add Mu metal over bellows on wastewater line.


Next Week:

  • Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
  • Unistrut mounting for cables - Neal will do when available
  • Engineering work on beam line starting

2 weeks:

  • Pull Heliax from Spectrum analyzer/Control room >> Buncher
  • 4th terminal system in Control room under assembly/rebuild
  • Items from To-do list...

Engineering Other business

Reports on Open Action Items:

Action Items: