Difference between revisions of "2021-08-04"
Jump to navigation
Jump to search
Line 29: | Line 29: | ||
DC Power: | DC Power: | ||
− | # [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. | + | *Trims: |
− | # [https://logbooks.jlab.org/entry/3889992 Wastewater beam line] trims cabled up. | + | *# [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. |
− | # Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad | + | *# [https://logbooks.jlab.org/entry/3889992 Wastewater beam line] trims cabled up. |
− | + | *# Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad | |
− | + | * [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 Solenoid PS] being installed. [https://logbooks.jlab.org/entry/3890134 Supply cabled and LCW hooked up]. | |
− | + | * MHB magnet re-designation to MLH to avoid confusion: Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets | |
+ | * Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!) | ||
Instrumentation and Controls: | Instrumentation and Controls: | ||
* BCM project software integration under way between Musson/Seaton and Sue Witherspoon | * BCM project software integration under way between Musson/Seaton and Sue Witherspoon | ||
− | * | + | |
+ | * Viewer system status [IC; Norris] | ||
*# Recable 2 viewers in keV whose channels were appropriated for HDice (done) | *# Recable 2 viewers in keV whose channels were appropriated for HDice (done) | ||
*# Reconnect IYGM401 (formerly ITV, now YAG) | *# Reconnect IYGM401 (formerly ITV, now YAG) | ||
*# Drag cable and connect IYGM603 and IYGM603 (appropriated from HDice line, swapped ITV > YAG). | *# Drag cable and connect IYGM603 and IYGM603 (appropriated from HDice line, swapped ITV > YAG). | ||
− | * Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required... | + | *# Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required... |
+ | |||
+ | |||
+ | |||
+ | |||
RF: | RF: |
Revision as of 19:03, 3 August 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
- To join via phone, use one of the following numbers and the Conference ID: 984025598.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- 8/9/21 Start Hot Check-out
New items for discussion:
Short term schedule update:
This week:
Reports by Group: CIS/EGG:
- Gun operating at 180kV w/o Field Emission
- HV tests with a GaAs puck (#8) in the gun (8/3) [Carlos]
- Gun HVPS locked out , reconnect gun valve, charge NF3, degas heater/puck, get UITF laser on (8/4)
- Make photocathode (8/5) [Joe/Max]
- Align laser to photocathode, using retro and QE (8/5) [Shukui]
- Gun rebuild wiki
DC Power:
- Trims:
- Trim magnets near gun re-cabled.
- Wastewater beam line trims cabled up.
- Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad
- Solenoid PS being installed. Supply cabled and LCW hooked up.
- MHB magnet re-designation to MLH to avoid confusion: Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets
- Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
Instrumentation and Controls:
- BCM project software integration under way between Musson/Seaton and Sue Witherspoon
- Viewer system status [IC; Norris]
- Recable 2 viewers in keV whose channels were appropriated for HDice (done)
- Reconnect IYGM401 (formerly ITV, now YAG)
- Drag cable and connect IYGM603 and IYGM603 (appropriated from HDice line, swapped ITV > YAG).
- Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required...
RF:
- 6GHz > 1.5GHz Down-converter installed for bunch length system
Vacuum:
SSG:
- BLM locations being set 7/21 following this meeting
- FSD inputs for magnet and BCM being prepared
ME / Installation:
- Pb stacked; RCG required modification due to permanent shielding req delay.
- New designs for FC3 and FC4 with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction!
- Songsheet being updated by Shaun; be sure to let him know when changes are made!
- Status of permanent shielding purchase?
Experiment:
- COO/ESAD/RSAD prepared; committee response in progress.
Other:
- EES work happening in earnest
- List of Engineering Jobs remaining
Still to do:
- Add Mu metal over bellows on wastewater line.
Next Week:
- Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Engineering work on beam line starting
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan) Strawman