Difference between revisions of "Meeting 7/28/22 - COMTRA"

From Ciswikidb
Jump to navigation Jump to search
Line 30: Line 30:
 
* BNL Stand - agreed w/ Cliff, will work up the order
 
* BNL Stand - agreed w/ Cliff, will work up the order
 
* Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
* Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
* Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => completed, Riad stored in UITF?
+
* Radiator '''(1) completed, (1) needed'''
 +
* Collimator - Fabricate (2) [[media:JL0015777_Cu_collimator.pdf]] => '''(2) completed'''
 
* Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => Machine Shop request in [https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm;jsessionid=72888DCB6ACFE194CC116F841A221DB1.cfusion?request_id=331095&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11 Shop job]
 
* Absorbers - Fabricate (6) [[media:Absorber - 240 D 001 14_V4.pdf]] => Machine Shop request in [https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm;jsessionid=72888DCB6ACFE194CC116F841A221DB1.cfusion?request_id=331095&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11 Shop job]
  

Revision as of 18:34, 27 July 2022

Thursday's @ 9am EDT by Zoom

7/28/22 Update

Analyzing Magnet
DAQ & RACK
  • PMT-5R ItoV amplifier (due TBD)
  • To-do => final cable, connector, rack layout
Detector
ME
2 X 4 X 4 – Need 11
2 X 4 X 6 – Need 2
2 X 4 X 8 – Need 99
Geant4 Model
Documentation