===7/28/22 Update===
+
===Analyzing Magnet===
;Analyzing Magnet
 
 
* Kepco PS ('''due week of Aug 8th''') => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
 
* Kepco PS ('''due week of Aug 8th''') => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412686
 
* Magnet '''(request 7/15)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
 
* Magnet '''(request 7/15)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412389
  
;DAQ & RACK
+
===DAQ & RACK===
 
* PMT-5R ItoV amplifier (due TBD)
 
* PMT-5R ItoV amplifier (due TBD)
 
* To-do => final cable, connector, rack layout
 
* To-do => final cable, connector, rack layout
  
;Detector
+
===Detector===
 
* BGO crystals - '''Arrived at JLab, stored in cabinet'''
 
* BGO crystals - '''Arrived at JLab, stored in cabinet'''
 
* PMTs '''(arrived 8/2)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
 
* PMTs '''(arrived 8/2)''' => https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=412467
Line 18: Line 17:
 
* Detector boxes '''(shipped, DHL estimate 8/9)'''
 
* Detector boxes '''(shipped, DHL estimate 8/9)'''
  
;ME
+
===ME===
* UITF Stand - PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
+
* New layout
** zero-length reducer 4.5 to 2.75. Do you want us to procure or do you want to search for one?
+
** zero-length reducer 4.5 to 2.75 - still need?
** Spool 4.25 lg. Do you want us to fab a new spool or do you want to search/ cut/reweld a spool? [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
+
** Spool 4.25 lg [[media:JL0029599-2068-SPOOL 1.50 DIA 2.75 NR X 2.75 ROT REV-, prelim.pdf]]
* UITF Lead
+
* Stands
 +
** UITF PR placed due 7/20 - https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=413412&approvalVersion=1
 +
* BNL Stand - agreed w/ Cliff, will work up the order
 +
** UITF Lead
 
:: 2 X 4 X 4 – Need 11
 
:: 2 X 4 X 4 – Need 11
 
:: 2 X 4 X 6 – Need 2
 
:: 2 X 4 X 6 – Need 2
 
:: 2 X 4 X 8 – Need 99
 
:: 2 X 4 X 8 – Need 99
* BNL Stand - agreed w/ Cliff, will work up the order
 
 
* Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
* Machine shop parts order (signed 7/15) => https://misportal.jlab.org/mis/apps/job_request/mshop/view_request.cfm?request_id=331093&CFID=9494961&CFTOKEN=12c0e13e2fdfe4c0-6A08D05A-D611-3C6A-FFFACAEF6E693E11
 
* Radiator '''(1) completed, (1) needed'''
 
* Radiator '''(1) completed, (1) needed'''

Revision as of 19:25, 3 August 2022

Thursday's @ 9am EDT by Zoom

Analyzing Magnet

DAQ & RACK

  • PMT-5R ItoV amplifier (due TBD)
  • To-do => final cable, connector, rack layout

Detector

ME

2 X 4 X 4 – Need 11
2 X 4 X 6 – Need 2
2 X 4 X 8 – Need 99
Geant4 Model
Documentation