Line 23: | Line 23: | ||
* FC2 Bellows | * FC2 Bellows | ||
* Bubble Run | * Bubble Run | ||
+ | ** Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber | ||
+ | ** Engineering run in August/September, ~couple weeks of running Day/Swing | ||
+ | ** Laser shuttering needed | ||
* Mott Run | * Mott Run | ||
+ | ** Run2 in August or September, maybe a long 4 day 24/7 weekend | ||
+ | ** No vacuum work planned, will use same gold foils as installed | ||
+ | ** Need 31MHz operation, low current <5 uA | ||
* Photocathode Swap (DBR) | * Photocathode Swap (DBR) | ||
== May 14, 2015 - Mandatory SAD Kickoff Safety Meeting == | == May 14, 2015 - Mandatory SAD Kickoff Safety Meeting == | ||
* CC 1:30pm | * CC 1:30pm |
Revision as of 07:11, 14 May 2015
April 3, 2015 - Work Plan Ideas
- Work Plans media:SAD15-Summer-CIS.xlsx
April 26, 2015 - Laser Planning Meeting
- Meeting/Summary April 16, 2015 - 3-Laser/4-Laser Discussion
May 11, 2015 - Suhring 1330 SAD Scheduling Meeting
- Task List (CIS dates tentative) media:150511_Suhring.docx
- Calendar View (CIS dates tentative) media:150511_1330.pptx
May 14, 2015 - CIS SAD Kickoff Meeting
- Laser
- Must = analog TEC control, similar seeds for similar pulse width
- Should = improved housing and cooling to diagnose work on lasers
- Like = Phase monitoring for testing purposes
- RF work
- Must = 3 RF spigots @ 250MHz + 2 RF spigots @ 499MHz
- Should = 360 phase control for all rep rates
- Like = Phase monitoring for testing purposes
- Gun2
- Bake History and Planning (Grames) media:150514_Gun2Bake.docx
- Brock Cavity
- FC2 Bellows
- Bubble Run
- Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber
- Engineering run in August/September, ~couple weeks of running Day/Swing
- Laser shuttering needed
- Mott Run
- Run2 in August or September, maybe a long 4 day 24/7 weekend
- No vacuum work planned, will use same gold foils as installed
- Need 31MHz operation, low current <5 uA
- Photocathode Swap (DBR)
May 14, 2015 - Mandatory SAD Kickoff Safety Meeting
- CC 1:30pm