(Created page with " * With both solenoids at +2.0 Amps, the solenoid field direction is pointing downstream along the beam path. Figure 2 shows the cabling of the solenoids. The field of the ma...") |
|||
Line 1: | Line 1: | ||
− | + | * With both solenoids at +2.0 Amps, the solenoid field direction is pointing downstream along the beam path. Figure 2 shows the cabling of the solenoids. The field of the magnetized gun solenoid is pointing out of the photocathode into the downstream direction. | |
+ | |||
+ | * Conditioned Gun at 300 kV with solenoid at 0 to 300 A, left to do it at: 325, 350, 375, and 400 A. | ||
+ | |||
+ | * Plan for next week (March 27, 2017): | ||
+ | # Monday, Tuesday and Wednesday: open in morning to install beamline but close in afternoon to run beam | ||
+ | # Thursday and Friday open all day for beamline bake |
Revision as of 15:39, 20 March 2017
- With both solenoids at +2.0 Amps, the solenoid field direction is pointing downstream along the beam path. Figure 2 shows the cabling of the solenoids. The field of the magnetized gun solenoid is pointing out of the photocathode into the downstream direction.
- Conditioned Gun at 300 kV with solenoid at 0 to 300 A, left to do it at: 325, 350, 375, and 400 A.
- Plan for next week (March 27, 2017):
- Monday, Tuesday and Wednesday: open in morning to install beamline but close in afternoon to run beam
- Thursday and Friday open all day for beamline bake