  • High current runs



  • Shutdown Plan:
  1. Install new YAG screen at viewer 3
  2. Fix existing harp and install 20 µm tungsten wire
  3. Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
  4. Replace leaky vent valve
  5. Replace bad ion pump


  • Next Shutdown – December 2017:
  1. Install TE011 cavity