Difference between revisions of "October 9, 2019"
Jump to navigation
Jump to search
(Created page with "; CEBAF == Program Now - May == Plans and Status rest of SAD == * Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start * Oct 14 - 18 : laser PQB...") |
|||
Line 1: | Line 1: | ||
− | + | == CEBAF for 7 Months == | |
+ | * Calendar for your wall [[media:191009_CIS.pptx]] | ||
+ | * [https://accweb.acc.jlab.org/calendar/ SAD Calendar until startup] | ||
− | + | = Plans and Status rest of SAD = | |
− | |||
− | |||
− | |||
* Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start | * Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start | ||
* Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning? | * Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning? | ||
Line 10: | Line 9: | ||
* Oct 28 - Nov 1 : Injector setup and PQB checkout | * Oct 28 - Nov 1 : Injector setup and PQB checkout | ||
− | + | = What fit's and doesn't = | |
* I don't think we have time for the Load chamber, little time | * I don't think we have time for the Load chamber, little time | ||
* Daniel will coordinate removing the big HVPS oil tank | * Daniel will coordinate removing the big HVPS oil tank | ||
− | + | = CREX jobs = | |
+ | *Laser Room | ||
+ | :Camera measurements (post fiber change) | ||
+ | :Spinning LP for A/B/C/D: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669 | ||
+ | :Transition Time recheck | ||
+ | :IA setting zero-finding | ||
+ | |||
+ | *Beam to FC#1 | ||
+ | :Cathode Rotation: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18799 | ||
+ | :IA/RTP/RWHP settings for all 4 lasers: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19670 | ||
+ | :Pos Diff Feedback to FC1/FC2: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18793 | ||
+ | |||
+ | *Beam to either FC2/ILD (end of injector) | ||
+ | :90Hz beam motion fix? | ||
+ | :PQB Health check to FC2 | ||
+ | :PQB Health check to ILD | ||
+ | |||
+ | *Beam to HallA | ||
+ | :Adiabatic Damping check? | ||
+ | :Dithering check? | ||
+ | |||
+ | *During Experiments (affects other halls, but also necessary for HallC to ensure we are minimizing their Aq well) | ||
+ | :PITA scans | ||
+ | :RHWP sweeps | ||
+ | |||
+ | *Post Experiment | ||
+ | :Spot size asymmetry measurements: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669 | ||
+ | |||
+ | == LERF == | ||
: Nov 1-4 HCO for isotope run (laser, photocathode, high voltage) | : Nov 1-4 HCO for isotope run (laser, photocathode, high voltage) | ||
: Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA | : Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA | ||
: Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA | : Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA | ||
− | + | == UITF == | |
− | + | == GTS == |
Revision as of 08:32, 9 October 2019
CEBAF for 7 Months
- Calendar for your wall media:191009_CIS.pptx
- SAD Calendar until startup
Plans and Status rest of SAD
- Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start
- Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning?
- Oct 21 - 25 : Make a photocathode, remove SF6 conditioning resistor, crane stuff out, clean up, start making beam w/ PQB checks
- Oct 28 - Nov 1 : Injector setup and PQB checkout
What fit's and doesn't
- I don't think we have time for the Load chamber, little time
- Daniel will coordinate removing the big HVPS oil tank
CREX jobs
- Laser Room
- Camera measurements (post fiber change)
- Spinning LP for A/B/C/D: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669
- Transition Time recheck
- IA setting zero-finding
- Beam to FC#1
- Cathode Rotation: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18799
- IA/RTP/RWHP settings for all 4 lasers: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19670
- Pos Diff Feedback to FC1/FC2: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18793
- Beam to either FC2/ILD (end of injector)
- 90Hz beam motion fix?
- PQB Health check to FC2
- PQB Health check to ILD
- Beam to HallA
- Adiabatic Damping check?
- Dithering check?
- During Experiments (affects other halls, but also necessary for HallC to ensure we are minimizing their Aq well)
- PITA scans
- RHWP sweeps
- Post Experiment
- Spot size asymmetry measurements: http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19669
LERF
- Nov 1-4 HCO for isotope run (laser, photocathode, high voltage)
- Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA
- Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA