2. (Grames) JLab Update | 2. (Grames) JLab Update | ||
− | ; Design, installation and released mechanical drawings are here \group\bubble\grames | + | ; Design, installation and released mechanical drawings (dipole + beam line) are here \group\bubble\grames |
* Beamline Assembly [[media:ACC2008000-1100.pdf]] | * Beamline Assembly [[media:ACC2008000-1100.pdf]] | ||
Revision as of 09:52, 6 August 2014
We will meet in TL 2236 on Wednesday August 6 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Moderator Passcode: 5978 Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
2. (Grames) JLab Update
- Design, installation and released mechanical drawings (dipole + beam line) are here \group\bubble\grames
- Beamline Assembly media:ACC2008000-1100.pdf
- Fabrication status
- Installation status
- Injector power restored 2 days ago, can resume work
- Phil coordinating installation of S&A + Installation group for new points & pedestals
- Vacuum parts assembly will begin soon, tunnel installation date TBD
- Instrumentation hook-ups and cable pulls by ~Labor Day
- Commissioning status
- Provided punch list to Director of Ops (vacation until mid-August)
- High level goals are beam line functionality & 100uA at highest energy on radiator
- Contacted Medical Imaging group (Jay's suggestion) regarding Brem characterization