− | * Accelerator Schedule: | + | * Accelerator 2015 Schedule: |
− | # | + | # SRF helium process of North Linac (NL): May 19 - July 12 |
+ | # UIM : July 12 - August 10 | ||
+ | # SRF helium process of South Linac (SL): August 10 - September 12 | ||
* Bubble Chamber Schedule: | * Bubble Chamber Schedule: | ||
− | # | + | # Install in JLab Injector (June) |
+ | # Bubble Chamber tests - No beam (July) | ||
+ | # Commissioning with beam (August - September) |
Revision as of 11:21, 23 February 2015
We will meet in TL 2221 on Wednesday February 18 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
Notes from this meeting:
- Bubble Chamber:
- Chamber is filled with mercury but there is a little leak.
- Tasks:
- Bubble Chamber beamline commissioning (February - May)
- Bubble Chamber at JLab (May)
- Review of equipment - Bubble Chamber (April)
- Review of operational procedures for this equipment (May)
- Accelerator 2015 Schedule:
- SRF helium process of North Linac (NL): May 19 - July 12
- UIM : July 12 - August 10
- SRF helium process of South Linac (SL): August 10 - September 12
- Bubble Chamber Schedule:
- Install in JLab Injector (June)
- Bubble Chamber tests - No beam (July)
- Commissioning with beam (August - September)