Difference between revisions of "Summer SAD 2015"

From Ciswikidb
Jump to navigation Jump to search
Line 23: Line 23:
 
* FC2 Bellows
 
* FC2 Bellows
 
* Bubble Run
 
* Bubble Run
 +
** Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber
 +
** Engineering run in August/September, ~couple weeks of running Day/Swing
 +
** Laser shuttering needed
 
* Mott Run
 
* Mott Run
 +
** Run2 in August or September, maybe a long 4 day 24/7 weekend
 +
** No vacuum work planned, will use same gold foils as installed
 +
** Need 31MHz operation, low current <5 uA
 
* Photocathode Swap (DBR)
 
* Photocathode Swap (DBR)
  
 
== May 14, 2015 - Mandatory SAD Kickoff Safety Meeting ==
 
== May 14, 2015 - Mandatory SAD Kickoff Safety Meeting ==
 
* CC 1:30pm
 
* CC 1:30pm

Revision as of 07:11, 14 May 2015

April 3, 2015 - Work Plan Ideas

April 26, 2015 - Laser Planning Meeting

May 11, 2015 - Suhring 1330 SAD Scheduling Meeting

May 14, 2015 - CIS SAD Kickoff Meeting

  • Laser
    • Must = analog TEC control, similar seeds for similar pulse width
    • Should = improved housing and cooling to diagnose work on lasers
    • Like = Phase monitoring for testing purposes
  • RF work
    • Must = 3 RF spigots @ 250MHz + 2 RF spigots @ 499MHz
    • Should = 360 phase control for all rep rates
    • Like = Phase monitoring for testing purposes
  • Gun2
  • Brock Cavity
  • FC2 Bellows
  • Bubble Run
    • Installation July 1-31, remove Pavel's cross, restore original beam line, add ANL Bubble chamber
    • Engineering run in August/September, ~couple weeks of running Day/Swing
    • Laser shuttering needed
  • Mott Run
    • Run2 in August or September, maybe a long 4 day 24/7 weekend
    • No vacuum work planned, will use same gold foils as installed
    • Need 31MHz operation, low current <5 uA
  • Photocathode Swap (DBR)

May 14, 2015 - Mandatory SAD Kickoff Safety Meeting

  • CC 1:30pm