+ | By Nov. 9th the following things MUST be accomplished. | ||
+ | |||
+ | 1. CW beam to the inline dump 85uA from A laser, 1uA from the D laser | ||
+ | |||
+ | 2. Wien setup for alignment of polarization to Hall-A on 5-pass | ||
+ | |||
+ | 3. Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6 | ||
+ | |||
+ | 4. Beam matched in the inj. chicane, ready for transport into the NL. | ||
+ | |||
+ | 5. All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane | ||
+ | |||
+ | 6. RF calibration tool fully developed (anticipate Nov. 2-7 DAYS) | ||
+ | |||
+ | 7. quad centering tool fully developed (anticipate Nov. 2-7 DAYS) | ||
+ | |||
Injector Tests and Calendar [[media:150929_InjectorTestList.xlsx]] [[media:150929_InjectorTestList.pdf]] | Injector Tests and Calendar [[media:150929_InjectorTestList.xlsx]] [[media:150929_InjectorTestList.pdf]] |
Revision as of 11:27, 30 September 2015
By Nov. 9th the following things MUST be accomplished.
1. CW beam to the inline dump 85uA from A laser, 1uA from the D laser
2. Wien setup for alignment of polarization to Hall-A on 5-pass
3. Quads, solenoids centered (where appropriate) and the determined BPMs SOF loaded, see item 6
4. Beam matched in the inj. chicane, ready for transport into the NL.
5. All lasers should produce beam with the same TWISS/emittance values as measured in the inj. chicane
6. RF calibration tool fully developed (anticipate Nov. 2-7 DAYS)
7. quad centering tool fully developed (anticipate Nov. 2-7 DAYS)
Injector Tests and Calendar media:150929_InjectorTestList.xlsx media:150929_InjectorTestList.pdf