Difference between revisions of "PQB Meeting November 5, 2015"
Jump to navigation
Jump to search
Line 20: | Line 20: | ||
## Parity DAQ in hall is basically ready. | ## Parity DAQ in hall is basically ready. | ||
## DAQ at injector is working but Rakitha was going to make some changes to data format to make it easier on our analysis package. | ## DAQ at injector is working but Rakitha was going to make some changes to data format to make it easier on our analysis package. | ||
+ | # QWeak halo target was installed in Hall A. New optimized halo target will be installed in 2016. | ||
# Ed Folts – Hall A beamline progress report: | # Ed Folts – Hall A beamline progress report: | ||
## Will break vacuum to take pictures of QWeak halo target. | ## Will break vacuum to take pictures of QWeak halo target. | ||
## May have to move a girder to free space for Moller polarimeter target (Y. Roblin imported changes those in model and everything is fine). | ## May have to move a girder to free space for Moller polarimeter target (Y. Roblin imported changes those in model and everything is fine). |
Revision as of 10:05, 5 November 2015
We will meet in TL 2236 Thursday November 5 at 1:00 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
- Beam Schedule:
- Injector: a lot of opportunities
- Accelerator: Nov 9, 2015 – Dec 21
- Beam to Hall A: Dec 6 – Dec 21
- 900 kW push to Hall-A
- 5-pass 11 GeV Mott vs Moeller/Compton: spin dance
- 1-pass 2.2 GeV Mott vs Moeller/Compton: spin dance
- Accelerator: Jan 28, 2016 – April 14
- B. Michaels – Parity DAQs:
- Parity DAQ in hall is basically ready.
- DAQ at injector is working but Rakitha was going to make some changes to data format to make it easier on our analysis package.
- QWeak halo target was installed in Hall A. New optimized halo target will be installed in 2016.
- Ed Folts – Hall A beamline progress report:
- Will break vacuum to take pictures of QWeak halo target.
- May have to move a girder to free space for Moller polarimeter target (Y. Roblin imported changes those in model and everything is fine).