=== Laser Status (John) === | === Laser Status (John) === | ||
− | 4th laser amplifier | + | Status for 4th laser amplifier, components to complete 4th laser + additional optical path |
− | |||
New RTP scheme | New RTP scheme | ||
− | New PSS shutter | + | New PSS shutter complete? |
+ | What else? | ||
=== SCAM-II (Roger) === | === SCAM-II (Roger) === | ||
+ | Status for SCAM-II development | ||
+ | Comment on additional requests / timeline: | ||
+ | 1. Kevin Jordan provide requirements for an auxiliary beam sync trigger, | ||
+ | 2. Michael Tiefenback say whether to retain Mizar board, or what Mizar-like functions desired | ||
+ | When do you want requirements document for SCAM-II finalized, already? | ||
+ | |||
+ | === LLRF (Tomasz) === | ||
+ | Status and review of last meeting action items or comments: | ||
− | + | 1. Finalize plans with (Sandip and Alex) LCLS-II digitizer boards? | |
+ | |||
+ | 2. | ||
+ | |||
+ | 3. FPGA could be LCLS or commercial, but Curt prefers we go path of LCLS | ||
+ | * Tomasz would do design and implement with Rama, Chad, Trent | ||
+ | * Provide technical specification to software by May | ||
+ | * Aim to develop and test in the March-April-May time frame | ||
+ | * Need to coordinate with software on final solution e.g. FPGA or PC104 | ||
+ | |||
+ | 4. Require GSET, PSET and switch for 250/500 | ||
+ | |||
+ | 5. John would like a digital output for RF on/off state for safe integration to laser amplifier |
Revision as of 11:12, 4 March 2016
We'll meet on Wednesday March 9 in TL-1227 for around-the-table updates preparing for the summer SAD 4-laser upgrade. The agenda below is meant to explore the different activities, please add/edit as makes sense, post material to share or send me in advance and I can add it.
Agenda
Schedule (Joe)
Discuss modified Summer SAD schedule, remind people of constraints
Laser Status (John)
Status for 4th laser amplifier, components to complete 4th laser + additional optical path New RTP scheme New PSS shutter complete? What else?
SCAM-II (Roger)
Status for SCAM-II development Comment on additional requests / timeline: 1. Kevin Jordan provide requirements for an auxiliary beam sync trigger, 2. Michael Tiefenback say whether to retain Mizar board, or what Mizar-like functions desired When do you want requirements document for SCAM-II finalized, already?
LLRF (Tomasz)
Status and review of last meeting action items or comments: 1. Finalize plans with (Sandip and Alex) LCLS-II digitizer boards?
2.
3. FPGA could be LCLS or commercial, but Curt prefers we go path of LCLS * Tomasz would do design and implement with Rama, Chad, Trent * Provide technical specification to software by May * Aim to develop and test in the March-April-May time frame * Need to coordinate with software on final solution e.g. FPGA or PC104
4. Require GSET, PSET and switch for 250/500
5. John would like a digital output for RF on/off state for safe integration to laser amplifier