Line 6: | Line 6: | ||
***4) we need to measure current on anode plate and current in the dump, via picoammeters | ***4) we need to measure current on anode plate and current in the dump, via picoammeters | ||
***5) we will read vacuum by monitoring the current on John's UHV ion pump power supplies, I think there are 5 ion pumps | ***5) we will read vacuum by monitoring the current on John's UHV ion pump power supplies, I think there are 5 ion pumps | ||
+ | ***6) Matt informed M. Bickley and Carlos briefed him on the GTS project. Pam Kjeldsen contacted Carlos to know about the GTS. | ||
** Near term plans include: | ** Near term plans include: | ||
***1) a tune mode generator to reduce duty factor of beam, to protect the viewers. need a clock for this | ***1) a tune mode generator to reduce duty factor of beam, to protect the viewers. need a clock for this |
Revision as of 10:14, 8 March 2016
- We met with J. Coleman, O. Garza, and P. Vasilauskis on Thursday March 3 to discuss the GTS timeline, and what is needed to instrument the beamline.
- The objective is to run beam in early May.
- 1) dc laser light making dc beam. Shukui thinks he has all the necessary epics control to adjust laser power and open/close a shutter
- 2) We need current supplies for two solenoids and up to four corrector pairs
- 3) we need to insert three pneumatic viewers and deliver video upstairs to a monitor
- 4) we need to measure current on anode plate and current in the dump, via picoammeters
- 5) we will read vacuum by monitoring the current on John's UHV ion pump power supplies, I think there are 5 ion pumps
- 6) Matt informed M. Bickley and Carlos briefed him on the GTS project. Pam Kjeldsen contacted Carlos to know about the GTS.
- Near term plans include:
- 1) a tune mode generator to reduce duty factor of beam, to protect the viewers. need a clock for this
- 2) better video cameras to grab images for emittance measurement (synched to the clock?)
- Then in August or September, Riad's solnoid arrives. Would be nice to have the 500A supply in place by then.
- The objective is to run beam in early May.