April 14, 2017 - 200kV gun upgrade meeting
Jump to navigation
Jump to search
200kV Gun
- Timeline/sequence for 200kV HV chamber
Gun2 NEG Tube
- Danny updated NEG tube media:NEGTUBE_MARCH31.pdf
Gun3 Removal
- Week May 8 to remove/replace Gun3 ATLIS task
Eliminating Gun Switch Software
- Kyle building a new screen, tracking to be ready in May or June
Spellman HVPS update
- John/Brad can now talk to HVPS
Radmon update
- Omar will NOT be ready w/ new system => plan on borrowing from LERF (or GTS?)