Agenda:

1- PQB Setup status media:190614_PQB.pptx media:190614_PQB.pdf

Start looking at PQB seriously about 4-5 days into receiving beam

2- Daniel/Paul - Status of Injector Online Parity monitoring

On-line plots updated ~30 sec pushed to logbook anyone can see, or in MCC w/ Hall A user logging in

3- Status of PQB feedback PV's

Feedback plots updated ~10 sec pushed to PV's in archiver once Hall A in production mode

4- Is RTP weekly measurement needed?

Not needed routinely, but may ask for occasional check, takes 19.8 minutes

5- 90Hz investigation

Root cause not identified, but only presents itself at HWien near -15 deg, will re-check w/ final setup and after spin dance

6- IHWP in/out updating of RTP PVs

Joe/Brian/Paul/Caryn to meet, evaluate options A (write/push values using GUI) or B (write directly to RTP cell voltages)