August 16, 2019
Jump to navigation
Jump to search
We'll meet Friday 8/16 in TL-2236 @ 9:30am
- CEBAF
- Now (+3 wks) - Run A & B
- Sep 9 (+4 wks) - HV chamber + 200kV beam
- Oct 7 (+2 wks) - PSS cert + Laser upgrade + Docking chamber
- Oct 22 (+3 wks) - HCO
- Nov 11 (+2 wks) - Restore CEBAF
- Nov 25 (+4 wks) Physics @ 2.2 GeV/pass
- A 150uA @ 499 MHz (1st pass), CREX parity violation experiment 30Hz w/ Wien flips
- B 100nA @ 250 MHz (5th pass), Polarized beam request
- C 30uA @ 250 MHz (5th pass), Polarized beam experiment
- D 900nA @ 250 MHz (5th pass), Unpolarized but must share with C
- Dec 19 (+holidays): Off, but machine kept in hot standby
- Jan 2 (+4 months) - Restart
- May 6 (+11 months) -Injector upgrade
- UITF
- Ongoing vacuum work at UITF media:190815_UITFaugust2019.PNG
- Fall plans
- LERF
- Near and long term goals
- GTS
- TGun status and workload