October 9, 2019
Jump to navigation
Jump to search
- CEBAF
== Program Now - May
Plans and Status rest of SAD
- Oct 7 - 11 : Gun bake, leak check, lasers ready, laser training, laser PQB start
- Oct 14 - 18 : laser PQB continues, Re-assemble instrumentation, HV cables, coordinate with PSS/Ops for HV ON, conditioning?
- Oct 21 - 25 : Make a photocathode, remove SF6 conditioning resistor, crane stuff out, clean up, start making beam w/ PQB checks
- Oct 28 - Nov 1 : Injector setup and PQB checkout
What fit's and doesn't
- I don't think we have time for the Load chamber, little time
- Daniel will coordinate removing the big HVPS oil tank
- LERF
- Nov 1-4 HCO for isotope run (laser, photocathode, high voltage)
- Nov 5-6 : 2 shifts/day commissioning run, ~60 pC @ 4 MHz, < 1 mA
- Dec TBD : another couple shifts, actual isotope run, ~60 pC @ 4 MHz < 1 mA
- UITF
- GTS