May 17, 2022 - updates
Jump to navigation
Jump to search
Updates
- Anode flange designed based on Injector Phase 1 but with two HV ports
- The used zero length reducer 10" to 4-1/2" flanges from the GTS that looks it has a been baked many times has been machined and is ready for welding the two tubes for the mini-CF HV feedthroughs
- Screen Design
- Bubba made screen sections based on Shaun's drawings from thin and thick wire mesh
- Marcy and Carlos looked at the screen sections fit inside the HV chamber, Carlos to talk to Bubba for making new screen sections. Goal is to finish this job by the end of this week.
- Define layout for installation in CEBAF injector
- Any updates from Shaun?
- Carlos measured the CEBAF and UITF 14" HV chambers lengths, flange to flange: both measured 18.9". Drawing shows 18.88" ( Media:HV chamber gun 14" diameter drawing.pdf). The 18" HV chamber measured 19.6" flange to flange, Lesker drawing shows 19.66" (media:LeskerPrint.pdf). Shaun to verify with S&A numbers and his model, but that means the 18" HV chamber is longer than the 14" HV chamber by 0.78".
- Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx
- Clean room in LERF Lab 3A
- Clean room has been cleared off
- Lights have been replaced
- Next is to clean up the clean room and keep it clean
- Carlos verified that there is nitrogen available in Lab 3A
- Other items
- We received a brand new Genie lift (400 lbs capacity) with counterweight.
Useful documents
Updates
TEAMS meeting link sent along with invite