GTS meeting 4 12 16
Jump to navigation
Jump to search
- Beamline
- Viewer solenoid control boxes have been wired up and installed.
- Bubba is working on the instrument air line
- Cathode prep chamber
- High voltage conditioning. [1]
- Kr processing up to 325 kV. Soaking overnight at 300 kV reduced FE from 1000 CPS to < 50 CPS.
- Needs more processing
- Barrel polishing surface characterization: Media:Surface characterization summary.pptx
- Chris Gould completed the set of samples (anodes and 1cmx1cm samples) characterization using optical ellipsometry
- Mamun is studying the square samples with the AFM, EDS, etc.
- GTS Schedule including LERF CIS requests