GTS Improvement List - Summer 2016

From Ciswikidb
Revision as of 12:12, 8 July 2016 by Suleiman (talk | contribs)
Jump to navigation Jump to search

Lasers

Preparation Chamber

1. Put a shield for RGA (to limit light scattering from RGA filament that causes photoemission from chamber components surface that gets coated with photocathode materials during evaporation.)

2. Redesign for anode ring to mount on a paddle with a bellow (to enable flexibility in operation.)

3. Recharge Sb boat.

4. Clean up view ports that got coated.

5. Redesign for shield paddle motion technique.

6. Add a RAV to isolate IP from chamber.

7. Add a K effusion source.

8. Redesign for top heater to operate with cathode negative bias configuration. Redesign of puck and heater stalk to hold puck by heater stalk, and eliminate need of bottom heater to serve as a transfer point. Need to use ceramic circuit breaker to electrically isolate puck.

9. Replace bottom heater with a view port.

10. Install puck with Fe foil for Kerr measurement?


HV Chamber

1. Replace isolated anode feed through with a a longer one that is rated to 5000 V (but first, Gary must check for cathode magnet clearance)

2. Replace leaky gate valve.

3. Replace HV ceramic insulator.

4. Replace HV shed.

5. Move chamber front support foot backward to free space for cathode solenoid.


Magnetized Cathode Solenoid

Beamline

1. Install a YAG screen on the third diagnostic cross (instead of the phosphorus screen).

2. Install slits in first and second diagnostic crosses.

3. Install a Faraday Cup for emittance measurements. Need a new picoammeter.

4. Install 4 more RadiaBeam steerers. Need Trim cards and cables.

5. Check dump ceramic break shield.

6. Degas dump further.