UITF Meeting - December 4, 2017
Jump to navigation
Jump to search
UITF first beam on a viewer by December 22 2017
Prep chamber and Gun:
- Loaded fresh bulk GaAs cathodes on puck 22 and 14, plus one strained GaAs in storage manipulator.
- Both gun and prep chamber baked after replacing Cs channels and NF3 leak valve.
- Gun high voltage conditioning in progress
- Successfully activated a bulk GaAs photocathode link Details here
What else to make “simple” beam?
Updates on Epics control of:
- UITF keV region song sheet (version 16)
- UED
- M. Joyce: "UED is populated with new KeV and KeVDump beam line"
- As-built keV beam line component sequence in UED
- Valves
- Are those still in Manual mode? What is needed to have EPICS control?
- Magnets
- Magnet summary screen in EPICS DONE!
- J. Grames working on setting up magnet hot checkout (K. Banks to terminate magnets near the gun, Wein, etc) polarity checks, B-magnitude measurements, etc
- Viewers
- B. Freeman: "So from the viewer screen I put one button that will launch my application (adviewer) with the first viewer. Use the drop down menu in the left hand corner to scroll through camera feeds. This will not be the final configuration of the viewer screen. I plan to add some more options for viewer applications. I will also document all of the URLs for each camera feed. But this should be enough to see the viewers. I have verified that they all work and connected to the "correct" viewer."
- Video to control room, DONE!
- See entry from C. Norris: link Viewer images in control room
- Current monitoring at cup, dump and apertures. Cables connected to ammeters
- Gun HV control: DONE!
- UHV ion pumps: DONE!
- Decarad (in progress)
- Water flow signal to fed card
- Comments on UITFList from P. Francis
- Comments from P. Francis: "Flow Switches for FC1/MS, A3/A4 and FC2/D1 have been tested and are working. (Phil is working on making a final water connection with A3/A4 water supply). No screens for Flow Switch status's are available yet. The Flow Switches function as FSD elements is not functional yet even tho 90% of the wiring is complete (just a fiber needs to be installed from the FSD electrical board to the FSD Fiber board). Not sure when the FSD portion will be working, its part is out of my hands as I have all the wiring complete and have good status's into the FSD electrical board."
- FC1/MS flow rate is .54 gpm with a trip point set at .44 gpm.
- A3/A4 flow rate is .8 gpm with a trip point set at .5 gpm.
- FC2/D1 flow rate is 1 gpm with a trip point set at .5 gpm.
- (Phil is working on making a final water connection with A3/A4 water supply)
- What else to fsd card? BLMs?
- BPMs? RF?
- Need to make sure all isolated structures are properly grounded (50 ohm termination) if not to be used during first beam tests.
- LASER
- RF to seed laser
- Attenuator
- Power meter
- x/y stage
- tune mode generator (SCAM?)
- Comment from J. Hansknecht: "We have a laser with tune mode generator to generate VL beam. We have a working attenuator. We are VERY close to a working XY stage. Certainly will have it when conditioning is completed. PSS is ready, but the final shutters were not officially certified. (would this matter?) I think they like to certify with beam anyway. We can also certify into the laser power meter. It is functional and on the laser screen along with all other laser controls."
- Epics screens
- Do we have a SAVE/RESTORE?
What else later? By Feb 5, hopefully sooner
- BPMs
- RF to buncher
- RF to choppers
- Water skids functional
- OSP for buncher and choppers
By February 5, 2018
- All cryo work complete
- All High Power RF work complete
- OSP for QCM approved
- ODH assessment, vent can on relief stack, penetrations filled, etc,
To do:
- Get another shed electrode made, since we will need this electrode for the gun we pull from the tunnel
- GN2 manifolds, clean polyflo
- Tools, tool boxes
- Vacuum cabinet, with vacuum hardware
- Aluminum foil
- Dress ion pump cables
R&D at UITF
- mA polarized beam lifetime tests, lifetime vs laser spot size (continue Joe’s work)
- Other lifetime studies: vs gun voltage, vs active area (3, 5, 7 mm), vs color of light, vs photocathode thickness and cleave plane, bulk vs superlattice
- Lifetime vs oxidant (NF3, N2O, O2)
- GaAs activated with Cs and Li: bi-alkali lifetime tests
- Wein as precipitator
- GaAs/GaAsP with and without DBR, GaAsSb/AlGaAs, and GaAsSb/AlGaAsP photocathode lifetime tests
- Add an H-cleaner to the prep chamber
- Brock cavity bunchlength measurements, vs buncher power, pump/probe test