May 11, 2018 - SAD Toolbox Meeting
Jump to navigation
Jump to search
Last Week-ish
- Bubble Run
- Added new harp w/ temporary controls
- Added ceramic break to radiator (shield aimed downstream), in series w/ FCUP
- Added Gumby (10 sec) laser shutter, tested w/ beam and remote enable/disable
- Added x-ray card to locate beam position
- Upgrade Preparations
- Tested HVPS to 300kV in SF6 tank at 15psi, and greater
- Suitcase added to Tee, bake ~48 hours up to 165C, Tee vacuum good <100's nA
- DecaRad installation below outrigger laser table started, heads/cables ready to dress
Today, Next Week and Beyond
- Bubble will continue to run until next Friday @ 8am
- S&A begin 200kV electrode measurements 5/11 (per last week's plan)
- Met w/ Jerry to review PSS integration plans media:SAD18_PSS_180511.xlsx
- PSS dipole measurements vs. expected gun voltage
- Upgrade Week 1 media:SAD_180510.docx