UITF Meeting - June 15, 2018

From Ciswikidb
Revision as of 11:37, 13 June 2018 by Poelker (talk | contribs)
Jump to navigation Jump to search

Tasks before running beam to HDIce for target commissioning



  1. Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
  1. Vacuum Group, build the MeV beamline
  1. Cryo: install the helium return line
  1. SRF, need a point of contact for all things related to QCM operation
  1. Electrical engineering: design and build the PSS BCM
  1. Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
  1. Magnet group: give us a third trim card rack
  1. RF group: klystrons, high power amplifier, solid state amp, water skids
  1. Vashek: finish specifying the shielding requirements, then we start moving lead
  1. R&D related to low current BPMs, suggest you take that on, with help from Engineering
  1. Operations Group should augment Joe's modeling, using a particle tracking code
  1. Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review
  1. Gun group needs to build a new photogun
  1. Need to operate the UITF on a daily basis.....