Tasks before running beam to HDIce for target commissioning
- Mechanical design, full time for next ~ 4 months, then intermittently (i.e., Shaun Gregory and company)
- Suggest we as the Vacuum Group to build the MeV beamline (my group can help)
- Cryo: install the helium return line, or be content to vent the helium to the test lab
- SRF, need a point of contact for all things related to QCM operation, it's still confusing to me who to talk to
- Electrical engineering: design and build the PSS BCM, our "credited control" to limit beam current/loss and prevent accidental exposure to xrays
- Electrical engineering: stripline BPMs, get them to work (not the pA BPMs were were talking about today)
- Magnet group: give us a third trim card rack
- RF group: klystrons, high power amplifier, solid state amp, water skids
- Vashek: finish specifying the shielding requirements, then we start moving lead
- R&D related to low current BPMs, suggest Andy take this on, with help from Engineering
- Operations Group should augment Joe's modeling, using a particle tracking code
- Safety: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review, lots of documents, lots of reviews
- Gun group needs to build a new photogun
- Need to operate the UITF on a daily basis.....
- Need access to liquid helium for weeks long periods of time (i.e., competition with LCLS)