Topics

200kV Gun
fasteners: ordered and due march 6th.
.015" wire: received and handed over.
sapphire roller: ordered and due april 12th.
alumina centering ring: ordered and due april 12th.
roller pin: machine shop working, requested due date of march 15th?
roller spring: machine shop working, requested due date of march 15th
 but will be late. material won't be in until next week. shop was slow in
 resolving vendor and material issues. submitted february 8th, resolved 
 and signed off february 27th. 
key: received and handed over.
aft end: machine shop working with requested due date of march 15th?
ring holder: received and handed over
Status of small shed cathode electrode
Spring SAD (April 15 - June 10)
List of info I e-mailed to Chris Gould media:190228_SA_request.xlsx
Danny's dwg for survey measurements [[media:190306_S&A CHECKLIST.pdf
Wien Filter
Link to the Wien filter upgrade page
Gabriel status update
Latest Layouts
Danny Gun region media:190123_gun_to_chopper.pdf
Danny Booster region media:LAYOUT14FEB19.pdf
Danny updated Reza's powerpoint file w/ new dimensions media:190306_Injector upgrade Choppers to Booster v01DM.pptx
Joe Gun + Booster notes media:190123_INJ.pptx