March 7, 2019 - Weekly AIPINJ Meeting
Jump to navigation
Jump to search
Topics
- 200kV Gun
- fasteners: ordered and due march 6th.
- .015" wire: received and handed over.
- sapphire roller: ordered and due april 12th.
- alumina centering ring: ordered and due april 12th.
- roller pin: machine shop working, requested due date of march 15th?
- roller spring: machine shop working, requested due date of march 15th but will be late. material won't be in until next week. shop was slow in resolving vendor and material issues. submitted february 8th, resolved and signed off february 27th.
- key: received and handed over.
- aft end: machine shop working with requested due date of march 15th?
- ring holder: received and handed over
- Status of small shed cathode electrode
- Spring SAD (April 15 - June 10)
- List of info I e-mailed to Chris Gould media:190228_SA_request.xlsx
- Danny's dwg for survey measurements media:190306_S&A CHECKLIST.pdf
- Wien Filter
- Link to the Wien filter upgrade page
- Gabriel status update
- Latest Layouts
- Danny Gun region media:190123_gun_to_chopper.pdf
- Danny Booster region media:LAYOUT14FEB19.pdf
- Danny updated Reza's powerpoint file w/ new dimensions media:190306_Injector upgrade Choppers to Booster v01DM.pptx
- Joe Gun + Booster notes media:190123_INJ.pptx