January 13, 2020 - Service providers

From Ciswikidb
Revision as of 09:43, 13 January 2020 by Grames (talk | contribs)
Jump to navigation Jump to search

Service providers discussion

Scope of 2020 SAD

  • Booster will remain at UITF in 2020 to commission HDIce, nominally moves to CEBAF in 2021 during summer SAD.
  • During the 2020 SAD we will...
-Make the gun operate a 200 kV (A: make present gun operate 200 kV, B: install new electrode)
-Reconfigure beam line extending from gun through chopper
-Commission the new gun and beam line with 200 keV beam

Beyond 2020 SAD

  • We will not modify the configuration downstream of chopper until new Booster goes in
-This means the capture and QCM remain until Booster installed
-This also means we'll operate the gun and beam line at 130 keV until that time too

Status of the 2020 beam line upgrade

  • Layout
-We have a preliminary ME layout, mainly to tally that everything will fit; notably we have a pretty good idea what everything will be
-CIS/INJ/CASA are evaluating exact sequence for functionality and to model the envelope, aiming to have this pretty well defined in Feb
-By end of Feb will be able to make a synopsis of before vs. after
  • On the topic of everything, how does this go:
Vacuum
-Valves, same number, maybe one less
-IPs, Marcy has as-is tally, should be OK, may need to order couple small pumps
-DP stations, new NEG's for Y- and DP chamber, otherwise the same
Magnets
-Solenoids (beamline+chopper), updated bids due Wed 1/15, anticipate quick turnaround
-Wien filters, PO written, coils due early march
-Still need two 20A PS installed
-Still need WIen filter HV PS, switches, cables installed
-15 deg dipole, bids received, anticipate PO within a ~week
-Haimons-style steering coils, should have enough in hand, will order spares once layout done
-Wien correction quads, TBD depends on layout/modeling, may re-use peanut quads initially