Phase 1 System Readiness
Revision as of 19:59, 4 May 2021 by Moser (talk | contribs) (→System Readiness / HCO Schedule (April '21))
CIS Jobs Leading to HCO & Commissioning (Jan 1 - Apr 30)
- 4/19/21 - Updated punchlist media:210419_CIS_HCO.docx
- 4/06/21 - Updated punchlist media:210406_CIS_HCO.docx
- 3/22/21 - Updated punchlist media:210322_CIS_HCO_v2.docx
I&C/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)
- I&C Jobs
- What to expect in tunnel?
- Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2)
- There is now a 3D CAD model from gun to chopper, I can share pics or see Gary Hays or Shaun Gregory
- Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)
* BPMs = Pete estimates 1 person x 5 days for all of the BPM hook-up and pre-beam checkout jobs
- 10 total - all unrotated
- 3 new style => NEG coated large bore (2.5" ID); mapped by Musson (Kx/Ky values available)
- 7 old style => 5.5" long end tapped
- Viewers
- 8 total - all chromox except ITV0I02 (YAG)
- Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
- Crash inhibit #2 : ITV0I02 and Harp IHA0I02
- Harps
- 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
- Wien HV
- Tony status update
* Current Monitoring - Pete estimates 1 person x 3 days for ItoV, Picoammeters, Gun FSD LCW waterflow interlocks)
- 3 total - same as before (PCUP, A1, A2)
- PCUP identical as before, just a new location
- A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
- A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
- Valves
- 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
- Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
- Beam line valve - VBV1I07 (same name), same all metal gate valve
- Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
- All 3 valves tied to UHV vacuum fault (100 uA limit)
- Ion pumps
- Marcy's final list media:210209_ion pump names.xlsx
- Software Jobs
- CED
- Michele or Gary can gives us an update
- Apps
- Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
- Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
- Screens
- I guess many screens auto-updated from CED, that's great
- Like with apps, will need name review; I guess system owners look at their own screens for oddities?
- What else for software?
Magnet/DC-Power/Software Jobs Leading to HCO & Commissioning (Apr 5 - Apr 30)
- DC/Magnet Jobs
- Spreadsheet updated 3/15 media:210315_Phase1_Magnet_Summary.xlsx
- Updated MHD field map due from JM/LL to GC
- Updated MFX (SW/CW) field map due from RS to GC
- Spreadsheet updated after further feedback media:210301_Phase1_Magnet_Summary_v3.xlsx
- Spreadsheet updated at 3/1 SAD planning meeting media:210301_Phase1_Magnet_Summary_v2.xlsx
- Spreadsheet initially media:210301_Phase1_Magnet_Summary.xlsx
- Software Jobs
- CED
- Apps
- Screens
- What else for software?
- Other magnet jobs
- (JM) Complete magnet table I circulated
- Done(JM/LL) Initial QW measurement and assessment (sufficient for CED), summarized for Gary
- (RS/GC) FG solenoid special hysteresis for Gary
- (RS/MJ) Magnet info for Inj Steer spin calculations
- (JM/JG) Decision on spare DR fabrication and alignment
- Done (LL/JK/JM) PSS kicker - does MMF have any responsibility here, maybe just PSS?
- Done (LL/JM) Second QW measurement, what's the scope here?
- Done (JM) When is the rotating coil stand ready?
- (JM/LL) Reconciling MHD discrepancy
- (LL) Report on QW
- (LL) Report on HD
- (LL) Report on PSS kicker
System Readiness / HCO Schedule (April '21)
For detailed plans for a given day and week, discussed at 830 toolbox meeting every weekday, see CIS Phase 1 work plans
Format: time: System (# of people)
Updated 4/22
April/May | Mon | Tue | Wed | Thu | Fri | Sa | Su |
---|---|---|---|---|---|---|---|
12th - 16th | Morning: Valve Controls (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: Valve Controls (1x) Morning: ItoV, Pico, FSD (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: Valve Controls (1x) Morning: ItoV, Pico, FSD (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: ItoV, Pico, FSD (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: ItoV, Pico, FSD (1x) Afternoon: Magnet Hook-Ups (2x) |
Magnet Hook-Ups (2x) | Magnet Hook-Ups (2x) |
19th - 23rd | Morning: BPMs (1x) Morning: Viewers (1x) Morning: Harps (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: BPMs (1x) Morning: Viewers (1x) Morning: Harps (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: BPMs (1x) Morning: Viewers (1x) Morning: Harps (1x) Afternoon: Magnet Hook-Ups (2x) |
Morning: Diagnostics Hook-ups as possible; Leak Checks (CIS) Bake Prep (all) Afternoon: Leak Checks Bake Prep (CIS) |
Morning: Diagnostics Hook-ups as possible Bake Prep (all) Afternoon: Bake Prep (all) |
Magnet Hook-Ups/HCO (2x)? |
Magnet Hook-Ups/HCO (2x)? |
26th - 30th | VBV1I070->0I07 Bake Opportunistic Hook-ups as possible |
VBV1I070->0I07 Bake Opportunistic Hook-ups as possible |
VBV1I070->0I07 Bake Opportunistic Hook-ups as possible |
VBV1I070->0I07 Bake Opportunistic Hook-ups as possible |
VBV1I070->0I07 Bake Opportunistic Hook-ups as possible |
Magnet HCO (2x)? | Magnet HCO (2x)? |
3rd - 7th | TBD | TBD | TBD | TBD | TBD | TBD | TBD |
10th - 14th | TBD | TBD | TBD | TBD | TBD | TBD | TBD |
- BPM = Francis
- Valve Controls = Ketchum
- ItoV, Picoammeters, Gun FSD Interlocks = Francis
- Viewers = Norris
- Harps = Dela Cruz
- Wien = Dela Cruz
- Magnet / DC Power = Coleman
- 2B Alignment = S&A, Gould
- PSS = Kowal